It is usual that organizations distribute the capacity of their resources
between several proyects. So a resource should be assigned with "max
units"=30% to project1, "max units"=20% to project2 and "max units"=50% to
project3. This feature is not supported in PS2007. Is there any way to
implement it?
Regards.