A
anovak
Folks,
I think I know the answer but wanted to get some feedback in case
there's something I'm missing.
I'm setting up Operational projects just for the purpose of capturing
actual work. No work is scheduled.
What I've noticed is there's no real difference between these two
approaches:
1. Set Duration to 0; assign resources at 100%
2. Assign Resources at 0% each
Thanks,
Andy
I think I know the answer but wanted to get some feedback in case
there's something I'm missing.
I'm setting up Operational projects just for the purpose of capturing
actual work. No work is scheduled.
What I've noticed is there's no real difference between these two
approaches:
1. Set Duration to 0; assign resources at 100%
2. Assign Resources at 0% each
Thanks,
Andy