T
Todduser
Hi all,
I’m using Project 2K3 and need to tie 2 tasks (that use 2 different
resources) together with 0 lag time (Task2 needs to start immediately after
Task1 is complete). An example:
Task1: Wash Car – Resource: CarWasher
Task2: Rinse Car – Resource: CarRinser
The soap should be immediately rinsed.
I need to have Task2 start immediately after Task1, and if the CarRinser
resource is booked, Task1 is never started until Project can schedule Task2
to immediately follow Task1.
Thank you
I’m using Project 2K3 and need to tie 2 tasks (that use 2 different
resources) together with 0 lag time (Task2 needs to start immediately after
Task1 is complete). An example:
Task1: Wash Car – Resource: CarWasher
Task2: Rinse Car – Resource: CarRinser
The soap should be immediately rinsed.
I need to have Task2 start immediately after Task1, and if the CarRinser
resource is booked, Task1 is never started until Project can schedule Task2
to immediately follow Task1.
Thank you