03 to 07 migration issues

M

mike

Hello, I am working with a client who recently converted from '03 to
'07. When the data on some projects came over, the work count changed
from flat to contoured. The oddity, is that if you insert the work
contour column, it is blank for every entry. The only way to see that
it is contoured is to go into Task Usage and click on the specific
resource, in the dialog box for work contour it indicates: Contoured.

With this in mind, the project file says that resource Mark King needs
to work on a task for 4 hours. The MS Project file says that the
resource worked on the task for
2 hours on August 11,
..5 hours on Oct 16
1.5 hours on Oct 17

On project Server, it is showing the resource worked
1.78 h on Aug 11
and
..22 hours Aug 12

Now the kicker. For the same resource on the same project, other
tasks came over just fine, with the default flat contour.

Any ideas on how this was caused, and how to remedy? Can I set the
task back to 0% complete, Publish, then go in and complete the tasks,
2 hrs on Aug 11 , two hrs on Oct 16 Publish.?

Mike
 
S

Sean Hanson

We have seen this in migrating data, we did data compares and about 10% of
the projects seem to experience this. I believe part of it is we had a change
in scheduling engine algorithms around Fixed Duration. Microsoft wanted it to
roll up much like Fixed Unit and Fixed Work from the assignments up to the
task. This was reversed with SP1. Make sure you are upgraded but this will
not help the schedules affected. Follow your approach in using Task Usage and
edit the tasks, then you should be fine there after.
--
Sean Hanson

http://www.randsmanagement.com
Mass Resource Tool for 2007
Project Server 2007 Archive Tool
2007 ULS Log Reporting
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top