G
Ger
I'm hoping someone can help me here. I keep coming up with
a problem (in MS Project 98, but may well apply to other
versions) where I need to book a resource for 1.5 days,
and I do so with 100% of their time. It then books the
resource against the task for a full 2 days.
I presume this is because I have entered 100%, but even if
I enter less it still spans 2 days - just lowers the
percentage of use.
What I want is to be able to have 100% for first day, and
50% for second day, therefore allowing me to book out the
resource for half of the second day without it being
flagged as overbooked.
Thanks in advance.
Gerrard
a problem (in MS Project 98, but may well apply to other
versions) where I need to book a resource for 1.5 days,
and I do so with 100% of their time. It then books the
resource against the task for a full 2 days.
I presume this is because I have entered 100%, but even if
I enter less it still spans 2 days - just lowers the
percentage of use.
What I want is to be able to have 100% for first day, and
50% for second day, therefore allowing me to book out the
resource for half of the second day without it being
flagged as overbooked.
Thanks in advance.
Gerrard