Lenny
Hi,
I have a enterprise resource that is working on two different
projects. One project requires 8 hours per day and the other project
requires 6.5 hours per day. How should that resource be set in the
system?
We have considered the following:
Resource calendars - but you can only use one per resource
Task calendars - seem like it would be an administrative nightmare and
it would impact any other resources on the task
Project calendar - seems to override the resource's hours on the 6.5
day project by changing the resources time to 8 hours.
Is this possible? Does anyone have a great solution/idea?
Thank you in advance for your time!
Lenny
I have a enterprise resource that is working on two different
projects. One project requires 8 hours per day and the other project
requires 6.5 hours per day. How should that resource be set in the
system?
We have considered the following:
Resource calendars - but you can only use one per resource
Task calendars - seem like it would be an administrative nightmare and
it would impact any other resources on the task
Project calendar - seems to override the resource's hours on the 6.5
day project by changing the resources time to 8 hours.
Is this possible? Does anyone have a great solution/idea?
Thank you in advance for your time!
Lenny