D
David Mauceli
I have two tasks in my project plan. One of them (Task 1)has multiple
resources working on it, and have a very high Work value (1440 hours). The
other task (Task 2) has one resource working on it (Lets call him resource
A). I have resource A working on the task 1 at 50%, and working on task 2 at
100%. However, when I resource level, resource A ends up working on task 1
for 20 hours a week until its done, then he works on task 2. I would like
resource A to work on task 2 while he is not working on task 1, and therefore
be fully utilized. What am I doing wrong?
resources working on it, and have a very high Work value (1440 hours). The
other task (Task 2) has one resource working on it (Lets call him resource
A). I have resource A working on the task 1 at 50%, and working on task 2 at
100%. However, when I resource level, resource A ends up working on task 1
for 20 hours a week until its done, then he works on task 2. I would like
resource A to work on task 2 while he is not working on task 1, and therefore
be fully utilized. What am I doing wrong?