1 task to multi people?

G

greg

I have a task that 1 am assigning to multiple people.
In the task>>resources tab I list the users.
what do I do with the units? keep them all 100%?
If I have 2 people do I make them both 50%?

thanks in advance
 
G

greg

thanks for the answer,



Jan De Messemaeker said:
The % is which part of THEIR time they will spend on teh task, not which
part of the task they will do.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
T

Travis Meyer

Under the resources you put the percentage of the time
they will spend on that task. For example you have 3
people working on one task for a week. One of them spends
all his time on it and the other two spend 30% of their
time. Hope this helps if not email me.
 
G

greg

thanks

Travis Meyer said:
Under the resources you put the percentage of the time
they will spend on that task. For example you have 3
people working on one task for a week. One of them spends
all his time on it and the other two spend 30% of their
time. Hope this helps if not email me.
 