100% complete tasks starting after todays date

C

confused

Hi,

Im quite new to ms project and am trying to track work.
I am doing the following:
1) project ->project information and change the status date to today
2) Update the status of tasks (using %complete)
3) tools->tracking->update project, reschedule uncompleted work to start
after today for entire project
4) level resources from today

However, tasks which 100 % complete appear as starting after today. anyone
know why this is happeneing?
thanks for any help
 
J

Jan De Messemaeker

Hi,

If they were planned after today setting them 100% complete leaves them
there and no leveling will move them.
 
M

Mike Glen

Hi ,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #25, 26 & 27 on progressing, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top