Hi,
Im quite new to ms project and am trying to track work.
I am doing the following:
1) project ->project information and change the status date to today
2) Update the status of tasks (using %complete)
3) tools->tracking->update project, reschedule uncompleted work to start
after today for entire project
4) level resources from today
However, tasks which 100 % complete appear as starting after today. anyone
know why this is happeneing?
thanks for any help