The tasks that are 100% complete are still displayed at my Resource's Web
access. I already republished the entire project and still are displayed. I
dont want them to click on HIDE TASK everytime it is 100%. I want to
automatically hide these tasks from their views.

Is there special option i should click on MS Project to resolve my issue on
100% task complete? I'm not sure if this is a bug of some sort? Does the (?)
at the end of my duration have an impact on this?

Not sure what to do now....

Help!

Pebbles

PS. Im really a newbie with MS-Project (barely a month to be exact) so
please bear with me :) Thanks!
 
G

Gerard Ducouret

Hello Pebbles
I'm afraid that you'll have to click on HIDE TASK everytime it is 100%.
There is no other way to do that... :-(

Gérard Ducouret [Project MVP]

"Pebbles the Great!" <Pebbles the [email protected]> a écrit
dans le message de
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top