I’m attempting to “close out†project plans. Is there a way to mark all the
tasks 100% complete without the Actual hours adjusting? Basically, I want to
close the tasks based on the actual hours currently attached to them. I’m
trying to avoid having to go to each individual task, recalculating, and
saving…

Please advise.

Thanks MK
 
J

James Fraser

MK said:
I’m attempting to “close out†project plans. Is there a way to mark all the
tasks 100% complete without the Actual hours adjusting?

Try changing Remaining Work to 0.


James Fraser
 