100% completed task has been reverted to 96%???

S

Sara

Hi

We have PS2003.

Here's my problem.
Some tasks which have been published to 100% are found as 96% a couple of
days later.... It seems effort hours has been decreased from 1 hour to 0.92
hour. Task type seems to have changed as well. Are there any unappropriate
work I might possibly have done?

Any support would be greatly appreciated.
 
G

Gordon

Hi Sara,

Have you changed the normal working day hrs from 8hrs to say 8.5hr? I am
guessing may be this situation could cause an 8hr day task represent itself
as .96days. Just a pointer.

Cheers,
 
S

Sara

Hi Gordon,

I have not changed hours.....
Just certain tasks only......
Is there any setting that I can check on the tasks?
 