100% completed tasks are shown in resources' My Tasks view

R

Rohit Agrawal

Hi,
We are facing the issue where 100% completed tasks are shown in My Tasks view.
I have checked task settings which are shown as below.
Task settings and display say as below
Current tasks are those tasks which:
1. have started but not yet finished,
2. or have been rejected and not yet resubmitted
3. or are not older than or further in the future more than 120 days.

According to point 1, only tasks that are not completed should be shown. Pls
advise.
Thanks.
 
D

Dale Howard [MVP]

Rohit --

What is your setting for a Current Task in Project Server 2007? If you are
using 120 days, then the My Tasks page will show task that a resource
completed in the last 120 days, or will start in the next 120 days.
Whatever value you specify is used to determine the "look back" period for
completed tasks and the "look ahead" period for upcoming tasks. Let us know
what you find.
 