%100 in Project 2003 and 0% complete in PWA

S

Scott

When tasks are updated w/ (for example) 100% completes in Project 2003 and
"published" I can understand why the same tasks in Project Web Access show
the tasks as 0% complete. My guess is that the update from the Resource
Manager (responsible to complete the task) in PWA is used to compare for
accuracy (maybe the task didn't get done). But when I look at old tasks in
PWA that were NEVER updated using PWA they eventally show as 100% complete to
match the M.S. Project 2003 schedule. Does anyone know the timetable for
when PWA uses the % complete in M.S. Project to update the PWA % complete
column?
 
M

Mike Glen

Hi Scott,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 
D

Dale Howard [MVP]

Scott --

Where in PWA? Project Center or detailed Project views? Or in the
timesheet on the View my tasks page?
 
D

Dale Howard [MVP]

Scott --

Whenever the PM receives, approves, and processes task updates into the
Microsoft Project plan, he/she should also click Collaborate - Publish - All
Information to "push" the latest schedule changes to every area of PWA. Is
this your current process?
 

Ask a Question