Hi:
One of my project managers insists on not using summary tasks in a project
of more than 1000 tasks. When I insert a summary task into this project, it
seems there is a 1K limit to the number of detail tasks per summary tasks
beyond which Project indents tasks on its own creating non-sensical breakdown
structures. Do you know if the 1K limit is a documented feature?
Thank you,
Christine