2-level RM & PM approval, "show timesheet status" field missing &

  • Thread starter Project Planner - University
  • Start date
P

Project Planner - University

PWA 2003

I've read the posts about the "show timesheet status" check field being
missing. I've tried to follow it to the letter, and I still can't get the
field to appear.

We would like the RMs to review hours prior to PM approvals (or, actually, I
should say the organization wants to), and from what I've read, if this were
all working correctly, an asterisk shows up next to the hours for those hours
NOT "pre-approved" by the resource manager.

Also, in order to just test this theory, I've only populated the RBS in a
limited manner.
 