M
Macrofinder
Class Module:
I am currently using Project 2000. I have written 2 separate class modules.
One event happens upon Project_BeforeClose and the other occurs on
Project_Open. I am unable to make both events work together. Can I have 2
separate application events work in my Global Project.mpt? Please advise.
DateDiff:
I have one of my duration fields set up as a custom ProjDatediff field.
Everything is working well, however it is calculating down to the
hour/minute. I would like it to calculate to the day (i.e. Finish4 =
12/12/05 8am and Finish = 12/12/05 4pm, calendar = standard, then Duration1 =
0d). Is this possible in a custom DateDiff field? If not, how do I
calculate a duration field to show the Datediff to the day??
Thank you so much. Happy New Year.
I am currently using Project 2000. I have written 2 separate class modules.
One event happens upon Project_BeforeClose and the other occurs on
Project_Open. I am unable to make both events work together. Can I have 2
separate application events work in my Global Project.mpt? Please advise.
DateDiff:
I have one of my duration fields set up as a custom ProjDatediff field.
Everything is working well, however it is calculating down to the
hour/minute. I would like it to calculate to the day (i.e. Finish4 =
12/12/05 8am and Finish = 12/12/05 4pm, calendar = standard, then Duration1 =
0d). Is this possible in a custom DateDiff field? If not, how do I
calculate a duration field to show the Datediff to the day??
Thank you so much. Happy New Year.