J
Jonathan
I have created a 5 day duration task with 2 resources assigned in Project
2007. One of these resources is going on vacation mid-way into this task, but
the other can continue in her absence.
I created a seperate enterprise calendar for her to account for her
unavailability and when I associated her calendar with the task, BOTH
resources were affected in that the task was pushed out until she returns to
work.
Is there a way to have the standard calendar settings applied to the 2nd
resource and the 'vacation' calendar apply to the lady while she is away -
FOR THE SAME TASK at the same time
or
is there a better way to manage this work of 2 resources? (like maybe split
the task into 2 separate tasks - one for the 1st resource and the 2nd for the
lady going on vacation)?
Thanks
2007. One of these resources is going on vacation mid-way into this task, but
the other can continue in her absence.
I created a seperate enterprise calendar for her to account for her
unavailability and when I associated her calendar with the task, BOTH
resources were affected in that the task was pushed out until she returns to
work.
Is there a way to have the standard calendar settings applied to the 2nd
resource and the 'vacation' calendar apply to the lady while she is away -
FOR THE SAME TASK at the same time
or
is there a better way to manage this work of 2 resources? (like maybe split
the task into 2 separate tasks - one for the 1st resource and the 2nd for the
lady going on vacation)?
Thanks