D
Dominic Moss
I have been working with a company that wants to rigorously protect their
project data. They want to have the following process in force.
Team members update progress on tasks - method set to update actuals per
time period - updates submitted to Project Managers.
Project Managers approve updates submitted by team members and then pass
updates to the Project Office.
Project Office approves updates and updates project plans with timesheet
information.
As far as I am aware the only way an out of the box Project Server instance
could handle this requirement would be through Delegation with the Project
Managers being the "Lead" in the delegation process - I explained this but
it was deemed too bureaucratic.
Does anyone know of a third party timesheet product that will integrate with
Project Server and allow the required process as described to be employed?
--
Dominic Moss
www.projectability.co.uk
Helping people achieve more with Microsoft Project
Tel +44 8707 303 400
Fax +44 8707 303 500
project data. They want to have the following process in force.
Team members update progress on tasks - method set to update actuals per
time period - updates submitted to Project Managers.
Project Managers approve updates submitted by team members and then pass
updates to the Project Office.
Project Office approves updates and updates project plans with timesheet
information.
As far as I am aware the only way an out of the box Project Server instance
could handle this requirement would be through Delegation with the Project
Managers being the "Lead" in the delegation process - I explained this but
it was deemed too bureaucratic.
Does anyone know of a third party timesheet product that will integrate with
Project Server and allow the required process as described to be employed?
--
Dominic Moss
www.projectability.co.uk
Helping people achieve more with Microsoft Project
Tel +44 8707 303 400
Fax +44 8707 303 500