J
jp
Hi,
I will be creating a project plan that has 2 tasks ie. Task5 & Task6.
These 2 tasks will be interacting with each other for at least 1 to 2 weeks.
That's because Task5 will try to complete all its work. However it is until
Task 6 reviews and finds more work that Task5 needs to complete.
How would I set these 2 tasks in ms-project 2003?
Thanks.
-jP
I will be creating a project plan that has 2 tasks ie. Task5 & Task6.
These 2 tasks will be interacting with each other for at least 1 to 2 weeks.
That's because Task5 will try to complete all its work. However it is until
Task 6 reviews and finds more work that Task5 needs to complete.
How would I set these 2 tasks in ms-project 2003?
Thanks.
-jP