M
Maleza
I've been running 2002 MS Project Professional and Project Server.
If I upgraded to 2003 desktop, I know there is a patch we could install
to run with 2002 server. Is that patch at the desktop level or on the
server?
Then, what happens with compatability with the project plans? Can
project plans produced by a 2003 desktop co-exist in the same 2002
Server with project plans produced by a 2002 desktop?
What if I did it the other way?--Upgrade to 2003 Server and keep 2002
desktop?--Would that work?
Any documentation, insight or advice on this would be very helpful.
Thanks,
Elvis
If I upgraded to 2003 desktop, I know there is a patch we could install
to run with 2002 server. Is that patch at the desktop level or on the
server?
Then, what happens with compatability with the project plans? Can
project plans produced by a 2003 desktop co-exist in the same 2002
Server with project plans produced by a 2002 desktop?
What if I did it the other way?--Upgrade to 2003 Server and keep 2002
desktop?--Would that work?
Any documentation, insight or advice on this would be very helpful.
Thanks,
Elvis