L
Langhorne
Project Server & Project Pro 2003:
We've discovered at least one instance where a number of hours from one
resource on one day on one task didn't print on the timesheet. The 15 hours
are there (yes, a long day) when viewing resource assignments or adjust
actuals, and viewed in Project Pro. But when the resource prints his
timesheet using the Timesheet View in View my Tasks, it's not there. All
other hours for all other tasks for that resource printed fine. We don't
have any timesheet add-ons or anything else fancy, just straight "Print Grid"
from View my Tasks.
Any ideas what might be causing that? Thanks.
We've discovered at least one instance where a number of hours from one
resource on one day on one task didn't print on the timesheet. The 15 hours
are there (yes, a long day) when viewing resource assignments or adjust
actuals, and viewed in Project Pro. But when the resource prints his
timesheet using the Timesheet View in View my Tasks, it's not there. All
other hours for all other tasks for that resource printed fine. We don't
have any timesheet add-ons or anything else fancy, just straight "Print Grid"
from View my Tasks.