D
Donna
Hi -
I have an organization that doesn't like Timesheets or how they are
implemented in 2007.....
Total Eng Org size is ~ 400 peope,
We have a 3 different overhead type of projects that have been created. Each
line represents a functional manager & their direct reports - so the
functional manager is the status manager and must approve. most are
approving via PWA.
Once they approve - they don't always publish.
When a project does get published - should it not publish all approved tasks
that are on the project? Why would some hours get removed if already
approved?
The Mgr and their Team members - all get their My Tasks reset to 0??
I'm stuck on this one....
??
I have an organization that doesn't like Timesheets or how they are
implemented in 2007.....
Total Eng Org size is ~ 400 peope,
We have a 3 different overhead type of projects that have been created. Each
line represents a functional manager & their direct reports - so the
functional manager is the status manager and must approve. most are
approving via PWA.
Once they approve - they don't always publish.
When a project does get published - should it not publish all approved tasks
that are on the project? Why would some hours get removed if already
approved?
The Mgr and their Team members - all get their My Tasks reset to 0??
I'm stuck on this one....
??