Mark E. Read
In Project Server 2007 I created a look up table and corresponding
field in the resource entity.
I have a number of resources to edit, so I want to edit them within
Project Pro 2007.
I check out the resources and add the column that I want to edit. The
drop down contains three of the same values from the lookup table, but
a different fourth (from another table...hmmm)
Thinking I'm crazy, I check in PWA and the lookup table looks fine.
I go to another workstation, and another instance of Project Pro 2007,
and bring up the resource sheet and add the column I want to use and
the values look fine.
Going back to the original workstation, I delete the global.mpt file,
and restart project.
Still no luck. Same four values, one of them incorrect.
What's my next step? Do I reinstall MS Project Pro 2007 on that
workstation?
field in the resource entity.
I have a number of resources to edit, so I want to edit them within
Project Pro 2007.
I check out the resources and add the column that I want to edit. The
drop down contains three of the same values from the lookup table, but
a different fourth (from another table...hmmm)
Thinking I'm crazy, I check in PWA and the lookup table looks fine.
I go to another workstation, and another instance of Project Pro 2007,
and bring up the resource sheet and add the column I want to use and
the values look fine.
Going back to the original workstation, I delete the global.mpt file,
and restart project.
Still no luck. Same four values, one of them incorrect.
What's my next step? Do I reinstall MS Project Pro 2007 on that
workstation?