Kerry
Using resource center - view assignments, it shows a resource with 66 hours
of remaining work for February, for a particular project. When I switch to
view availability, it shows that the resource is still assigned to 99.4 hrs,
for that same project, for the last weeks of this month.
We're training our PM's to use resource center to monitor overallocations.
After receiving an email from the PM for this project, I believed it was an
overallocation problem. This resource was overallocated for the month, but
completed a lot of work early. As result, the overallocation problem was
resolved, but view assignments is still showing the problem.
Is this is a bug?
of remaining work for February, for a particular project. When I switch to
view availability, it shows that the resource is still assigned to 99.4 hrs,
for that same project, for the last weeks of this month.
We're training our PM's to use resource center to monitor overallocations.
After receiving an email from the PM for this project, I believed it was an
overallocation problem. This resource was overallocated for the month, but
completed a lot of work early. As result, the overallocation problem was
resolved, but view assignments is still showing the problem.
Is this is a bug?