Project desktop expert, new to Project Server 2007 and working with a sandbox
implementation currently.
When I use the PWA Build Team...Replace to replace a generic resource on a
project with an actual named resource after first publishing a plan, my
updates don't appear to be reflected in Project Server. If I check out and
open the Project Plan in MSP Pro, however, the updates were made, and then if
I publish the schedule, the updates appear in server.
I thought when you made resource updates using PWA that they should be
reflected immediately (or as soon as the request is thru the queue).
implementation currently.
When I use the PWA Build Team...Replace to replace a generic resource on a
project with an actual named resource after first publishing a plan, my
updates don't appear to be reflected in Project Server. If I check out and
open the Project Plan in MSP Pro, however, the updates were made, and then if
I publish the schedule, the updates appear in server.
I thought when you made resource updates using PWA that they should be
reflected immediately (or as soon as the request is thru the queue).