24 hour calender 7 days a week in 3 team shift

A

Assist

We work 8 hours in 3 turns 24/7. Project calendar is 24 hours (24H/day,
168H/month and 30days/month) and Resource calendar is 24 hours .

Task is fixed work = 2760H and given duration = 10days. This example gives
1150% Resource Units. I expected 3 times as much, 3450%.

Can project calculate the number resources needed for the task?
 
S

Steve House

If your resource calendar shows 24 hours per day working hours, that mean
that ONE man working 100% will perform 24 man-hours of work during 24 hours
of duration. A total of 2760 man-hours of required work to complete the
task spread over a duration of 10 24-hour days means that each day 276
man-hours of work will need to be accomplished. 276 hours/24 hours per man
= 11.5 men are required, thus 1150% resource units. It also implies that
none of them will get any time off for the full 10 day period and that's not
likely - machines might work like that but humans simply can't do it and
survive! It's not for nothing that around 6 to 8 hours per day is the
defacto standard workday - that's a biologically driven limit to human
endurance for 100% functioning beyond which productivity plummets into the
toilet and accident rates soar. IMHO it's an incredibly bad practice to
routinely schedule people for 10, 12, or 14 hour days and from a purely
economic standpoint a firm or manager that does it formally or informally is
shooting themselves in the foot, incurring long term costs that far exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT reflect the hours
of business of the organization. Rather, it should reflect the work hours
of ONE typical generic resource because a task breakdown is down down to the
level of a task being a package of work done by ONE resource or resource
teak working together and when you add a task to your project you want it to
be scheduled reflecting that reality. The 24 hour project calendar says
that work proceeds on all tasks 24/7 but that not usual in most project.
Since tasks are typically assigned to one person and one person typically
only works about 8 hours per day, the task schedule should reflect that it
proceeds at the rate of 8 hours per day between start and finish. Likewise,
the resource calendar should NOT be a 24 hour calendar because the resource
calendar for Joe Resource reflects Joe's personal working schedule and no
human being works 24/7 for days on end without a break, without a meal,
without even a nap or what have you yet that's exactly what the 24 hour
calendar says is your physical reality. If you have 3 shifts covering in
total the 24 hour period, you have not one resource calendar but three - one
for days, one for swing, and one for grave. If you have a grouped resource,
like a group of 15 welders and different members of the group work on each
shift - say 7 on days, 6 on swing, and 2 on grave - you would have three
resources listed - day welders max 700%, swing welders max 600% and grave
welders max 200% and each group would have the base calendar that describes
their shift's hours of work. If you are listing single individuals as
resources, like Joe Engineer, you assign him the base calendar that most
accurately describes his individual hours of work, modified as needed to
reflect his true working hours and vacation time, etc. Now if I have a task
starting Monday 8am requiring 24 hours of work and I assign 1 day shift
worker to it, it will finish Wed at 5pm. IF I assign two day shift workers,
it will finish Tue 12 noon (if it's effort driven) But if I assign 1 day
shift worker and 1 swing shift worker it will finish Tue 5pm (day works mon
day, swing works mon swing, task stops at midnight and resumes when day guy
comes back in on Tue morning.) If I assign one guy from each shift, the
task will run 24 consecutive hours and starting Mon 8am will finish Tue at
8am, exactly as expected, right? (I omitted taking into account their
possible overlap in hours for simplicity - Mon between 3 and 5 you'd
probably get 4 hours of work done instead of 2 since both guys are working
together during that period but you get the idea).

HTH
 
A

Assist

Hi Steve
Extremely fine answer. I will try out your ideas and get back with my results.

A little more info:
Our line of business is in aircraft maintenance, and strongly regulated. We
work 8 hours in 3 shifts. The effective work is about 7 hours or less in one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task and we have
the aircraft on the ground for max. amount of days (by contract with
customer). So the only variable is resources internally and externally.
Regards, Brian from Assist


Steve House said:
If your resource calendar shows 24 hours per day working hours, that mean
that ONE man working 100% will perform 24 man-hours of work during 24 hours
of duration. A total of 2760 man-hours of required work to complete the
task spread over a duration of 10 24-hour days means that each day 276
man-hours of work will need to be accomplished. 276 hours/24 hours per man
= 11.5 men are required, thus 1150% resource units. It also implies that
none of them will get any time off for the full 10 day period and that's not
likely - machines might work like that but humans simply can't do it and
survive! It's not for nothing that around 6 to 8 hours per day is the
defacto standard workday - that's a biologically driven limit to human
endurance for 100% functioning beyond which productivity plummets into the
toilet and accident rates soar. IMHO it's an incredibly bad practice to
routinely schedule people for 10, 12, or 14 hour days and from a purely
economic standpoint a firm or manager that does it formally or informally is
shooting themselves in the foot, incurring long term costs that far exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT reflect the hours
of business of the organization. Rather, it should reflect the work hours
of ONE typical generic resource because a task breakdown is down down to the
level of a task being a package of work done by ONE resource or resource
teak working together and when you add a task to your project you want it to
be scheduled reflecting that reality. The 24 hour project calendar says
that work proceeds on all tasks 24/7 but that not usual in most project.
Since tasks are typically assigned to one person and one person typically
only works about 8 hours per day, the task schedule should reflect that it
proceeds at the rate of 8 hours per day between start and finish. Likewise,
the resource calendar should NOT be a 24 hour calendar because the resource
calendar for Joe Resource reflects Joe's personal working schedule and no
human being works 24/7 for days on end without a break, without a meal,
without even a nap or what have you yet that's exactly what the 24 hour
calendar says is your physical reality. If you have 3 shifts covering in
total the 24 hour period, you have not one resource calendar but three - one
for days, one for swing, and one for grave. If you have a grouped resource,
like a group of 15 welders and different members of the group work on each
shift - say 7 on days, 6 on swing, and 2 on grave - you would have three
resources listed - day welders max 700%, swing welders max 600% and grave
welders max 200% and each group would have the base calendar that describes
their shift's hours of work. If you are listing single individuals as
resources, like Joe Engineer, you assign him the base calendar that most
accurately describes his individual hours of work, modified as needed to
reflect his true working hours and vacation time, etc. Now if I have a task
starting Monday 8am requiring 24 hours of work and I assign 1 day shift
worker to it, it will finish Wed at 5pm. IF I assign two day shift workers,
it will finish Tue 12 noon (if it's effort driven) But if I assign 1 day
shift worker and 1 swing shift worker it will finish Tue 5pm (day works mon
day, swing works mon swing, task stops at midnight and resumes when day guy
comes back in on Tue morning.) If I assign one guy from each shift, the
task will run 24 consecutive hours and starting Mon 8am will finish Tue at
8am, exactly as expected, right? (I omitted taking into account their
possible overlap in hours for simplicity - Mon between 3 and 5 you'd
probably get 4 hours of work done instead of 2 since both guys are working
together during that period but you get the idea).

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

Assist said:
We work 8 hours in 3 turns 24/7. Project calendar is 24 hours (24H/day,
168H/month and 30days/month) and Resource calendar is 24 hours .

Task is fixed work = 2760H and given duration = 10days. This example gives
1150% Resource Units. I expected 3 times as much, 3450%.

Can project calculate the number resources needed for the task?
 
S

Steve House

One thing to consider. The duration of a task is not normally the "window
of opportunity" within which the task must be done. Rather it's length of
time between when work on the job physically commences and when it is
complete. For a simple example, imagine an incoming aircraft requiring only
a single maintenance item that requires 1 person to perform 8 man-hours of
work. The plane arrives tomorrow morning and must be completed within 10
days. The nature of the work is such that once he starts on it, the
resource must focus 100% of his effort on that specific job - he can't
'multitask' that activity with other responsibilities. That task is NOT a
10 day duration task. Rather it is a 1 day duration task with a completion
deadline 10 days out. If he CAN multitask and split his time 50/50 between
that task and something else (and you choose to schedule him for both of
them), it is a 2 day task with the resource assigned 50% and a deadline 10
days out, and so forth. If two people can share the task with each devoting
their full effort towards it, then each of them is doing 100% effort and
each performs 4 hours of the 8 total required and it's a 1/2 day duration
task with a deadline 10 days out. In each case it is either a .5 or 1 or 2
day duration task occurring within a 10 day window between when it could
start and when it must be done. It's generally assumed that you always want
to schedule it to start AND END as early as possible within that window and
would never want lower the resource effort level in order to spread the
duration to fill the time to the deadline unless you have no other choice -
your objective is to "git 'er done" as soon as you possibly can that is
consistent with the other priorities falling outside the project's universe
and that can be done with the manpower available .

Tasks are always observable physical activity of some sort being performed
by a resource. The duration is simply the time period over which an
observer will see action taking place on that specific activity as
distinguished from the time period over which he 'might' see activity, if
you get the difference.

HTH and best of luck

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Assist said:
Hi Steve
Extremely fine answer. I will try out your ideas and get back with my
results.

A little more info:
Our line of business is in aircraft maintenance, and strongly regulated.
We
work 8 hours in 3 shifts. The effective work is about 7 hours or less in
one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task and we
have
the aircraft on the ground for max. amount of days (by contract with
customer). So the only variable is resources internally and externally.
Regards, Brian from Assist


Steve House said:
If your resource calendar shows 24 hours per day working hours, that mean
that ONE man working 100% will perform 24 man-hours of work during 24
hours
of duration. A total of 2760 man-hours of required work to complete the
task spread over a duration of 10 24-hour days means that each day 276
man-hours of work will need to be accomplished. 276 hours/24 hours per
man
= 11.5 men are required, thus 1150% resource units. It also implies that
none of them will get any time off for the full 10 day period and that's
not
likely - machines might work like that but humans simply can't do it and
survive! It's not for nothing that around 6 to 8 hours per day is the
defacto standard workday - that's a biologically driven limit to human
endurance for 100% functioning beyond which productivity plummets into
the
toilet and accident rates soar. IMHO it's an incredibly bad practice to
routinely schedule people for 10, 12, or 14 hour days and from a purely
economic standpoint a firm or manager that does it formally or informally
is
shooting themselves in the foot, incurring long term costs that far
exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT reflect the
hours
of business of the organization. Rather, it should reflect the work
hours
of ONE typical generic resource because a task breakdown is down down to
the
level of a task being a package of work done by ONE resource or resource
teak working together and when you add a task to your project you want it
to
be scheduled reflecting that reality. The 24 hour project calendar says
that work proceeds on all tasks 24/7 but that not usual in most project.
Since tasks are typically assigned to one person and one person typically
only works about 8 hours per day, the task schedule should reflect that
it
proceeds at the rate of 8 hours per day between start and finish.
Likewise,
the resource calendar should NOT be a 24 hour calendar because the
resource
calendar for Joe Resource reflects Joe's personal working schedule and no
human being works 24/7 for days on end without a break, without a meal,
without even a nap or what have you yet that's exactly what the 24 hour
calendar says is your physical reality. If you have 3 shifts covering in
total the 24 hour period, you have not one resource calendar but three -
one
for days, one for swing, and one for grave. If you have a grouped
resource,
like a group of 15 welders and different members of the group work on
each
shift - say 7 on days, 6 on swing, and 2 on grave - you would have three
resources listed - day welders max 700%, swing welders max 600% and grave
welders max 200% and each group would have the base calendar that
describes
their shift's hours of work. If you are listing single individuals as
resources, like Joe Engineer, you assign him the base calendar that most
accurately describes his individual hours of work, modified as needed to
reflect his true working hours and vacation time, etc. Now if I have a
task
starting Monday 8am requiring 24 hours of work and I assign 1 day shift
worker to it, it will finish Wed at 5pm. IF I assign two day shift
workers,
it will finish Tue 12 noon (if it's effort driven) But if I assign 1 day
shift worker and 1 swing shift worker it will finish Tue 5pm (day works
mon
day, swing works mon swing, task stops at midnight and resumes when day
guy
comes back in on Tue morning.) If I assign one guy from each shift, the
task will run 24 consecutive hours and starting Mon 8am will finish Tue
at
8am, exactly as expected, right? (I omitted taking into account their
possible overlap in hours for simplicity - Mon between 3 and 5 you'd
probably get 4 hours of work done instead of 2 since both guys are
working
together during that period but you get the idea).

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

Assist said:
We work 8 hours in 3 turns 24/7. Project calendar is 24 hours (24H/day,
168H/month and 30days/month) and Resource calendar is 24 hours .

Task is fixed work = 2760H and given duration = 10days. This example
gives
1150% Resource Units. I expected 3 times as much, 3450%.

Can project calculate the number resources needed for the task?
 
A

Assist

Lets see if I got i right.
Generaly this is not what project is designed for. Do you recoment not to
use Project for this kind of tasks?


Steve House said:
One thing to consider. The duration of a task is not normally the "window
of opportunity" within which the task must be done. Rather it's length of
time between when work on the job physically commences and when it is
complete. For a simple example, imagine an incoming aircraft requiring only
a single maintenance item that requires 1 person to perform 8 man-hours of
work. The plane arrives tomorrow morning and must be completed within 10
days. The nature of the work is such that once he starts on it, the
resource must focus 100% of his effort on that specific job - he can't
'multitask' that activity with other responsibilities. That task is NOT a
10 day duration task. Rather it is a 1 day duration task with a completion
deadline 10 days out. If he CAN multitask and split his time 50/50 between
that task and something else (and you choose to schedule him for both of
them), it is a 2 day task with the resource assigned 50% and a deadline 10
days out, and so forth. If two people can share the task with each devoting
their full effort towards it, then each of them is doing 100% effort and
each performs 4 hours of the 8 total required and it's a 1/2 day duration
task with a deadline 10 days out. In each case it is either a .5 or 1 or 2
day duration task occurring within a 10 day window between when it could
start and when it must be done. It's generally assumed that you always want
to schedule it to start AND END as early as possible within that window and
would never want lower the resource effort level in order to spread the
duration to fill the time to the deadline unless you have no other choice -
your objective is to "git 'er done" as soon as you possibly can that is
consistent with the other priorities falling outside the project's universe
and that can be done with the manpower available .

Tasks are always observable physical activity of some sort being performed
by a resource. The duration is simply the time period over which an
observer will see action taking place on that specific activity as
distinguished from the time period over which he 'might' see activity, if
you get the difference.

HTH and best of luck

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Assist said:
Hi Steve
Extremely fine answer. I will try out your ideas and get back with my
results.

A little more info:
Our line of business is in aircraft maintenance, and strongly regulated.
We
work 8 hours in 3 shifts. The effective work is about 7 hours or less in
one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task and we
have
the aircraft on the ground for max. amount of days (by contract with
customer). So the only variable is resources internally and externally.
Regards, Brian from Assist


Steve House said:
If your resource calendar shows 24 hours per day working hours, that mean
that ONE man working 100% will perform 24 man-hours of work during 24
hours
of duration. A total of 2760 man-hours of required work to complete the
task spread over a duration of 10 24-hour days means that each day 276
man-hours of work will need to be accomplished. 276 hours/24 hours per
man
= 11.5 men are required, thus 1150% resource units. It also implies that
none of them will get any time off for the full 10 day period and that's
not
likely - machines might work like that but humans simply can't do it and
survive! It's not for nothing that around 6 to 8 hours per day is the
defacto standard workday - that's a biologically driven limit to human
endurance for 100% functioning beyond which productivity plummets into
the
toilet and accident rates soar. IMHO it's an incredibly bad practice to
routinely schedule people for 10, 12, or 14 hour days and from a purely
economic standpoint a firm or manager that does it formally or informally
is
shooting themselves in the foot, incurring long term costs that far
exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT reflect the
hours
of business of the organization. Rather, it should reflect the work
hours
of ONE typical generic resource because a task breakdown is down down to
the
level of a task being a package of work done by ONE resource or resource
teak working together and when you add a task to your project you want it
to
be scheduled reflecting that reality. The 24 hour project calendar says
that work proceeds on all tasks 24/7 but that not usual in most project.
Since tasks are typically assigned to one person and one person typically
only works about 8 hours per day, the task schedule should reflect that
it
proceeds at the rate of 8 hours per day between start and finish.
Likewise,
the resource calendar should NOT be a 24 hour calendar because the
resource
calendar for Joe Resource reflects Joe's personal working schedule and no
human being works 24/7 for days on end without a break, without a meal,
without even a nap or what have you yet that's exactly what the 24 hour
calendar says is your physical reality. If you have 3 shifts covering in
total the 24 hour period, you have not one resource calendar but three -
one
for days, one for swing, and one for grave. If you have a grouped
resource,
like a group of 15 welders and different members of the group work on
each
shift - say 7 on days, 6 on swing, and 2 on grave - you would have three
resources listed - day welders max 700%, swing welders max 600% and grave
welders max 200% and each group would have the base calendar that
describes
their shift's hours of work. If you are listing single individuals as
resources, like Joe Engineer, you assign him the base calendar that most
accurately describes his individual hours of work, modified as needed to
reflect his true working hours and vacation time, etc. Now if I have a
task
starting Monday 8am requiring 24 hours of work and I assign 1 day shift
worker to it, it will finish Wed at 5pm. IF I assign two day shift
workers,
it will finish Tue 12 noon (if it's effort driven) But if I assign 1 day
shift worker and 1 swing shift worker it will finish Tue 5pm (day works
mon
day, swing works mon swing, task stops at midnight and resumes when day
guy
comes back in on Tue morning.) If I assign one guy from each shift, the
task will run 24 consecutive hours and starting Mon 8am will finish Tue
at
8am, exactly as expected, right? (I omitted taking into account their
possible overlap in hours for simplicity - Mon between 3 and 5 you'd
probably get 4 hours of work done instead of 2 since both guys are
working
together during that period but you get the idea).

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

We work 8 hours in 3 turns 24/7. Project calendar is 24 hours (24H/day,
168H/month and 30days/month) and Resource calendar is 24 hours .

Task is fixed work = 2760H and given duration = 10days. This example
gives
1150% Resource Units. I expected 3 times as much, 3450%.

Can project calculate the number resources needed for the task?
 
S

Steve House

No no, not saying that at all! Quite the contrary - IMHO Project is an
excellent tool to use for this sort of thing. The periodic maintainance of
an individual aircraft can very easily be viewed as a project with
observable start and ending times and a unique deliverable being created.
But Project - as does adopting formal Critical Path Methodology in general,
even when done by paper and pencil - sometimes requires a fresh approach in
the way one looks at work and scheduling within your organization. For
example, it may be you're not presently looking at your manpower scheduling
at a fine enough detail to effectively manage the individual workers and
their individual tasks. "Inspect Engines" is not detailed enough. "Inspect
#1 Engine" is getting better. "Drop # 1 Engine (2 hours)," "Remove Cowling"
(1 hour), "X-ray #1 Engine's Main Turbine Blades" (6 hours) etc etc is
getting close. Idealy it needs to get down to the point you can use
Project's task list and calculated schedule to determine that an A&P
mechanic needs to show up at a specific location at a clearly identifiable
date and time with the appropriate parts and tools required to do a specific
task on a specific part of the airplane and he will be forecast to have
completed it by another specific date and time so that a) you know when he
can move on to something else that needs his skills to proceed; and b)
whoever has to do the next thing in line after him in that part of the
airplane knows when the first mechanic will be done and out of the way so
that HE can show up ready to do his part of the job.

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



Assist said:
Lets see if I got i right.
Generaly this is not what project is designed for. Do you recoment not to
use Project for this kind of tasks?


Steve House said:
One thing to consider. The duration of a task is not normally the
"window
of opportunity" within which the task must be done. Rather it's length
of
time between when work on the job physically commences and when it is
complete. For a simple example, imagine an incoming aircraft requiring
only
a single maintenance item that requires 1 person to perform 8 man-hours
of
work. The plane arrives tomorrow morning and must be completed within 10
days. The nature of the work is such that once he starts on it, the
resource must focus 100% of his effort on that specific job - he can't
'multitask' that activity with other responsibilities. That task is NOT
a
10 day duration task. Rather it is a 1 day duration task with a
completion
deadline 10 days out. If he CAN multitask and split his time 50/50
between
that task and something else (and you choose to schedule him for both of
them), it is a 2 day task with the resource assigned 50% and a deadline
10
days out, and so forth. If two people can share the task with each
devoting
their full effort towards it, then each of them is doing 100% effort and
each performs 4 hours of the 8 total required and it's a 1/2 day duration
task with a deadline 10 days out. In each case it is either a .5 or 1 or
2
day duration task occurring within a 10 day window between when it could
start and when it must be done. It's generally assumed that you always
want
to schedule it to start AND END as early as possible within that window
and
would never want lower the resource effort level in order to spread the
duration to fill the time to the deadline unless you have no other
choice -
your objective is to "git 'er done" as soon as you possibly can that is
consistent with the other priorities falling outside the project's
universe
and that can be done with the manpower available .

Tasks are always observable physical activity of some sort being
performed
by a resource. The duration is simply the time period over which an
observer will see action taking place on that specific activity as
distinguished from the time period over which he 'might' see activity, if
you get the difference.

HTH and best of luck

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Assist said:
Hi Steve
Extremely fine answer. I will try out your ideas and get back with my
results.

A little more info:
Our line of business is in aircraft maintenance, and strongly
regulated.
We
work 8 hours in 3 shifts. The effective work is about 7 hours or less
in
one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task and we
have
the aircraft on the ground for max. amount of days (by contract with
customer). So the only variable is resources internally and externally.
Regards, Brian from Assist


:

If your resource calendar shows 24 hours per day working hours, that
mean
that ONE man working 100% will perform 24 man-hours of work during 24
hours
of duration. A total of 2760 man-hours of required work to complete
the
task spread over a duration of 10 24-hour days means that each day 276
man-hours of work will need to be accomplished. 276 hours/24 hours
per
man
= 11.5 men are required, thus 1150% resource units. It also implies
that
none of them will get any time off for the full 10 day period and
that's
not
likely - machines might work like that but humans simply can't do it
and
survive! It's not for nothing that around 6 to 8 hours per day is the
defacto standard workday - that's a biologically driven limit to human
endurance for 100% functioning beyond which productivity plummets into
the
toilet and accident rates soar. IMHO it's an incredibly bad practice
to
routinely schedule people for 10, 12, or 14 hour days and from a
purely
economic standpoint a firm or manager that does it formally or
informally
is
shooting themselves in the foot, incurring long term costs that far
exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT reflect the
hours
of business of the organization. Rather, it should reflect the work
hours
of ONE typical generic resource because a task breakdown is down down
to
the
level of a task being a package of work done by ONE resource or
resource
teak working together and when you add a task to your project you want
it
to
be scheduled reflecting that reality. The 24 hour project calendar
says
that work proceeds on all tasks 24/7 but that not usual in most
project.
Since tasks are typically assigned to one person and one person
typically
only works about 8 hours per day, the task schedule should reflect
that
it
proceeds at the rate of 8 hours per day between start and finish.
Likewise,
the resource calendar should NOT be a 24 hour calendar because the
resource
calendar for Joe Resource reflects Joe's personal working schedule and
no
human being works 24/7 for days on end without a break, without a
meal,
without even a nap or what have you yet that's exactly what the 24
hour
calendar says is your physical reality. If you have 3 shifts covering
in
total the 24 hour period, you have not one resource calendar but
three -
one
for days, one for swing, and one for grave. If you have a grouped
resource,
like a group of 15 welders and different members of the group work on
each
shift - say 7 on days, 6 on swing, and 2 on grave - you would have
three
resources listed - day welders max 700%, swing welders max 600% and
grave
welders max 200% and each group would have the base calendar that
describes
their shift's hours of work. If you are listing single individuals as
resources, like Joe Engineer, you assign him the base calendar that
most
accurately describes his individual hours of work, modified as needed
to
reflect his true working hours and vacation time, etc. Now if I have
a
task
starting Monday 8am requiring 24 hours of work and I assign 1 day
shift
worker to it, it will finish Wed at 5pm. IF I assign two day shift
workers,
it will finish Tue 12 noon (if it's effort driven) But if I assign 1
day
shift worker and 1 swing shift worker it will finish Tue 5pm (day
works
mon
day, swing works mon swing, task stops at midnight and resumes when
day
guy
comes back in on Tue morning.) If I assign one guy from each shift,
the
task will run 24 consecutive hours and starting Mon 8am will finish
Tue
at
8am, exactly as expected, right? (I omitted taking into account their
possible overlap in hours for simplicity - Mon between 3 and 5 you'd
probably get 4 hours of work done instead of 2 since both guys are
working
together during that period but you get the idea).

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

We work 8 hours in 3 turns 24/7. Project calendar is 24 hours
(24H/day,
168H/month and 30days/month) and Resource calendar is 24 hours .

Task is fixed work = 2760H and given duration = 10days. This example
gives
1150% Resource Units. I expected 3 times as much, 3450%.

Can project calculate the number resources needed for the task?
 
A

Assist

Thanks a lot for your replies !
We use AMIGO to manage work cards on the different jobs. (We like to dig
data out of AMIGO and import it into MS Project, but that’s another story).
We like to show the big picture in a Gantt chart. So a C-Check on a specific
aircraft is one task. We are trying to use MS Project to show witch aircraft
is worked on (in which hangar) from start date to end date as one task.
We also want to show what kind of resource % that is needed. We like to show
the Gantt Chart on a big screen in the hangar as a service information to the
mechanics. At this point we won't use project to manage the mechanics
detailed tasks. If we need to hire in extra mechanics we like to know when,
how long and how many.

The question to us is how can MS Project calculate the need of resources
correct?

Example:
Project Calendar: 24/7, 8h/d, 40h/w, 30d/m
Task name: MS-AMM, C-Check
Duration: 10 days
Start date: 1-Oct-2007
Deadline is 10-oct-2007

Work: 2760h, Fixed work
Resource: Mechanics

Resource Calendar: I hope we can use one resource calendar, 24/7, 8h/d,
40h/w and 30d/m.
Resource name: Mechanics (There is only one kind of resources)
Unit: 12000% (120 mechanics) (+ hired-in mechanics if needed)

Regards,
Brian




Steve House said:
No no, not saying that at all! Quite the contrary - IMHO Project is an
excellent tool to use for this sort of thing. The periodic maintainance of
an individual aircraft can very easily be viewed as a project with
observable start and ending times and a unique deliverable being created.
But Project - as does adopting formal Critical Path Methodology in general,
even when done by paper and pencil - sometimes requires a fresh approach in
the way one looks at work and scheduling within your organization. For
example, it may be you're not presently looking at your manpower scheduling
at a fine enough detail to effectively manage the individual workers and
their individual tasks. "Inspect Engines" is not detailed enough. "Inspect
#1 Engine" is getting better. "Drop # 1 Engine (2 hours)," "Remove Cowling"
(1 hour), "X-ray #1 Engine's Main Turbine Blades" (6 hours) etc etc is
getting close. Idealy it needs to get down to the point you can use
Project's task list and calculated schedule to determine that an A&P
mechanic needs to show up at a specific location at a clearly identifiable
date and time with the appropriate parts and tools required to do a specific
task on a specific part of the airplane and he will be forecast to have
completed it by another specific date and time so that a) you know when he
can move on to something else that needs his skills to proceed; and b)
whoever has to do the next thing in line after him in that part of the
airplane knows when the first mechanic will be done and out of the way so
that HE can show up ready to do his part of the job.

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



Assist said:
Lets see if I got i right.
Generaly this is not what project is designed for. Do you recoment not to
use Project for this kind of tasks?


Steve House said:
One thing to consider. The duration of a task is not normally the
"window
of opportunity" within which the task must be done. Rather it's length
of
time between when work on the job physically commences and when it is
complete. For a simple example, imagine an incoming aircraft requiring
only
a single maintenance item that requires 1 person to perform 8 man-hours
of
work. The plane arrives tomorrow morning and must be completed within 10
days. The nature of the work is such that once he starts on it, the
resource must focus 100% of his effort on that specific job - he can't
'multitask' that activity with other responsibilities. That task is NOT
a
10 day duration task. Rather it is a 1 day duration task with a
completion
deadline 10 days out. If he CAN multitask and split his time 50/50
between
that task and something else (and you choose to schedule him for both of
them), it is a 2 day task with the resource assigned 50% and a deadline
10
days out, and so forth. If two people can share the task with each
devoting
their full effort towards it, then each of them is doing 100% effort and
each performs 4 hours of the 8 total required and it's a 1/2 day duration
task with a deadline 10 days out. In each case it is either a .5 or 1 or
2
day duration task occurring within a 10 day window between when it could
start and when it must be done. It's generally assumed that you always
want
to schedule it to start AND END as early as possible within that window
and
would never want lower the resource effort level in order to spread the
duration to fill the time to the deadline unless you have no other
choice -
your objective is to "git 'er done" as soon as you possibly can that is
consistent with the other priorities falling outside the project's
universe
and that can be done with the manpower available .

Tasks are always observable physical activity of some sort being
performed
by a resource. The duration is simply the time period over which an
observer will see action taking place on that specific activity as
distinguished from the time period over which he 'might' see activity, if
you get the difference.

HTH and best of luck

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Hi Steve
Extremely fine answer. I will try out your ideas and get back with my
results.

A little more info:
Our line of business is in aircraft maintenance, and strongly
regulated.
We
work 8 hours in 3 shifts. The effective work is about 7 hours or less
in
one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task and we
have
the aircraft on the ground for max. amount of days (by contract with
customer). So the only variable is resources internally and externally.
Regards, Brian from Assist


:

If your resource calendar shows 24 hours per day working hours, that
mean
that ONE man working 100% will perform 24 man-hours of work during 24
hours
of duration. A total of 2760 man-hours of required work to complete
the
task spread over a duration of 10 24-hour days means that each day 276
man-hours of work will need to be accomplished. 276 hours/24 hours
per
man
= 11.5 men are required, thus 1150% resource units. It also implies
that
none of them will get any time off for the full 10 day period and
that's
not
likely - machines might work like that but humans simply can't do it
and
survive! It's not for nothing that around 6 to 8 hours per day is the
defacto standard workday - that's a biologically driven limit to human
endurance for 100% functioning beyond which productivity plummets into
the
toilet and accident rates soar. IMHO it's an incredibly bad practice
to
routinely schedule people for 10, 12, or 14 hour days and from a
purely
economic standpoint a firm or manager that does it formally or
informally
is
shooting themselves in the foot, incurring long term costs that far
exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT reflect the
hours
of business of the organization. Rather, it should reflect the work
hours
of ONE typical generic resource because a task breakdown is down down
to
the
level of a task being a package of work done by ONE resource or
resource
teak working together and when you add a task to your project you want
it
to
be scheduled reflecting that reality. The 24 hour project calendar
says
that work proceeds on all tasks 24/7 but that not usual in most
project.
Since tasks are typically assigned to one person and one person
typically
only works about 8 hours per day, the task schedule should reflect
that
it
proceeds at the rate of 8 hours per day between start and finish.
Likewise,
the resource calendar should NOT be a 24 hour calendar because the
resource
calendar for Joe Resource reflects Joe's personal working schedule and
no
human being works 24/7 for days on end without a break, without a
meal,
without even a nap or what have you yet that's exactly what the 24
hour
calendar says is your physical reality. If you have 3 shifts covering
in
total the 24 hour period, you have not one resource calendar but
three -
one
for days, one for swing, and one for grave. If you have a grouped
resource,
like a group of 15 welders and different members of the group work on
each
shift - say 7 on days, 6 on swing, and 2 on grave - you would have
three
resources listed - day welders max 700%, swing welders max 600% and
grave
welders max 200% and each group would have the base calendar that
describes
their shift's hours of work. If you are listing single individuals as
resources, like Joe Engineer, you assign him the base calendar that
most
accurately describes his individual hours of work, modified as needed
to
reflect his true working hours and vacation time, etc. Now if I have
a
task
starting Monday 8am requiring 24 hours of work and I assign 1 day
shift
worker to it, it will finish Wed at 5pm. IF I assign two day shift
workers,
it will finish Tue 12 noon (if it's effort driven) But if I assign 1
day
shift worker and 1 swing shift worker it will finish Tue 5pm (day
works
mon
day, swing works mon swing, task stops at midnight and resumes when
day
guy
comes back in on Tue morning.) If I assign one guy from each shift,
the
task will run 24 consecutive hours and starting Mon 8am will finish
Tue
at
8am, exactly as expected, right? (I omitted taking into account their
possible overlap in hours for simplicity - Mon between 3 and 5 you'd
probably get 4 hours of work done instead of 2 since both guys are
working
together during that period but you get the idea).

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

We work 8 hours in 3 turns 24/7. Project calendar is 24 hours
(24H/day,
168H/month and 30days/month) and Resource calendar is 24 hours .

Task is fixed work = 2760H and given duration = 10days. This example
gives
1150% Resource Units. I expected 3 times as much, 3450%.

Can project calculate the number resources needed for the task?
 
S

Steve House

Question about your calendars. Remember durations are *always* stored and
processed internally in hours to the nearest 1/10 minute. Units such as
days, weeks, etc are provided as a convenience but are converted upon entry
and the "hors per day" etc setting on the calendar options page are the
conversion factors used. So when you say a task has a duration of "1 day"
are you thinking that task lasts 8 hours or does it last 24 hours? In other
words, if that 1-day duration task starts Monday at 8am should the schedule
have it end Monday at 5pm or Tuesday at 8am?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Assist said:
Thanks a lot for your replies !
We use AMIGO to manage work cards on the different jobs. (We like to dig
data out of AMIGO and import it into MS Project, but thatâ?Ts another
story).
We like to show the big picture in a Gantt chart. So a C-Check on a
specific
aircraft is one task. We are trying to use MS Project to show witch
aircraft
is worked on (in which hangar) from start date to end date as one task.
We also want to show what kind of resource % that is needed. We like to
show
the Gantt Chart on a big screen in the hangar as a service information to
the
mechanics. At this point we won't use project to manage the mechanics
detailed tasks. If we need to hire in extra mechanics we like to know
when,
how long and how many.

The question to us is how can MS Project calculate the need of resources
correct?

Example:
Project Calendar: 24/7, 8h/d, 40h/w, 30d/m
Task name: MS-AMM, C-Check
Duration: 10 days
Start date: 1-Oct-2007
Deadline is 10-oct-2007

Work: 2760h, Fixed work
Resource: Mechanics

Resource Calendar: I hope we can use one resource calendar, 24/7, 8h/d,
40h/w and 30d/m.
Resource name: Mechanics (There is only one kind of resources)
Unit: 12000% (120 mechanics) (+ hired-in mechanics if needed)

Regards,
Brian




Steve House said:
No no, not saying that at all! Quite the contrary - IMHO Project is an
excellent tool to use for this sort of thing. The periodic maintainance
of
an individual aircraft can very easily be viewed as a project with
observable start and ending times and a unique deliverable being created.
But Project - as does adopting formal Critical Path Methodology in
general,
even when done by paper and pencil - sometimes requires a fresh approach
in
the way one looks at work and scheduling within your organization. For
example, it may be you're not presently looking at your manpower
scheduling
at a fine enough detail to effectively manage the individual workers and
their individual tasks. "Inspect Engines" is not detailed enough.
"Inspect
#1 Engine" is getting better. "Drop # 1 Engine (2 hours)," "Remove
Cowling"
(1 hour), "X-ray #1 Engine's Main Turbine Blades" (6 hours) etc etc is
getting close. Idealy it needs to get down to the point you can use
Project's task list and calculated schedule to determine that an A&P
mechanic needs to show up at a specific location at a clearly
identifiable
date and time with the appropriate parts and tools required to do a
specific
task on a specific part of the airplane and he will be forecast to have
completed it by another specific date and time so that a) you know when
he
can move on to something else that needs his skills to proceed; and b)
whoever has to do the next thing in line after him in that part of the
airplane knows when the first mechanic will be done and out of the way so
that HE can show up ready to do his part of the job.

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



Assist said:
Lets see if I got i right.
Generaly this is not what project is designed for. Do you recoment not
to
use Project for this kind of tasks?


:

One thing to consider. The duration of a task is not normally the
"window
of opportunity" within which the task must be done. Rather it's
length
of
time between when work on the job physically commences and when it is
complete. For a simple example, imagine an incoming aircraft
requiring
only
a single maintenance item that requires 1 person to perform 8
man-hours
of
work. The plane arrives tomorrow morning and must be completed within
10
days. The nature of the work is such that once he starts on it, the
resource must focus 100% of his effort on that specific job - he
can't
'multitask' that activity with other responsibilities. That task is
NOT
a
10 day duration task. Rather it is a 1 day duration task with a
completion
deadline 10 days out. If he CAN multitask and split his time 50/50
between
that task and something else (and you choose to schedule him for both
of
them), it is a 2 day task with the resource assigned 50% and a
deadline
10
days out, and so forth. If two people can share the task with each
devoting
their full effort towards it, then each of them is doing 100% effort
and
each performs 4 hours of the 8 total required and it's a 1/2 day
duration
task with a deadline 10 days out. In each case it is either a .5 or 1
or
2
day duration task occurring within a 10 day window between when it
could
start and when it must be done. It's generally assumed that you
always
want
to schedule it to start AND END as early as possible within that
window
and
would never want lower the resource effort level in order to spread
the
duration to fill the time to the deadline unless you have no other
choice -
your objective is to "git 'er done" as soon as you possibly can that
is
consistent with the other priorities falling outside the project's
universe
and that can be done with the manpower available .

Tasks are always observable physical activity of some sort being
performed
by a resource. The duration is simply the time period over which an
observer will see action taking place on that specific activity as
distinguished from the time period over which he 'might' see activity,
if
you get the difference.

HTH and best of luck

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Hi Steve
Extremely fine answer. I will try out your ideas and get back with
my
results.

A little more info:
Our line of business is in aircraft maintenance, and strongly
regulated.
We
work 8 hours in 3 shifts. The effective work is about 7 hours or
less
in
one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task and
we
have
the aircraft on the ground for max. amount of days (by contract with
customer). So the only variable is resources internally and
externally.
Regards, Brian from Assist


:

If your resource calendar shows 24 hours per day working hours,
that
mean
that ONE man working 100% will perform 24 man-hours of work during
24
hours
of duration. A total of 2760 man-hours of required work to
complete
the
task spread over a duration of 10 24-hour days means that each day
276
man-hours of work will need to be accomplished. 276 hours/24 hours
per
man
= 11.5 men are required, thus 1150% resource units. It also
implies
that
none of them will get any time off for the full 10 day period and
that's
not
likely - machines might work like that but humans simply can't do
it
and
survive! It's not for nothing that around 6 to 8 hours per day is
the
defacto standard workday - that's a biologically driven limit to
human
endurance for 100% functioning beyond which productivity plummets
into
the
toilet and accident rates soar. IMHO it's an incredibly bad
practice
to
routinely schedule people for 10, 12, or 14 hour days and from a
purely
economic standpoint a firm or manager that does it formally or
informally
is
shooting themselves in the foot, incurring long term costs that far
exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT reflect
the
hours
of business of the organization. Rather, it should reflect the
work
hours
of ONE typical generic resource because a task breakdown is down
down
to
the
level of a task being a package of work done by ONE resource or
resource
teak working together and when you add a task to your project you
want
it
to
be scheduled reflecting that reality. The 24 hour project calendar
says
that work proceeds on all tasks 24/7 but that not usual in most
project.
Since tasks are typically assigned to one person and one person
typically
only works about 8 hours per day, the task schedule should reflect
that
it
proceeds at the rate of 8 hours per day between start and finish.
Likewise,
the resource calendar should NOT be a 24 hour calendar because the
resource
calendar for Joe Resource reflects Joe's personal working schedule
and
no
human being works 24/7 for days on end without a break, without a
meal,
without even a nap or what have you yet that's exactly what the 24
hour
calendar says is your physical reality. If you have 3 shifts
covering
in
total the 24 hour period, you have not one resource calendar but
three -
one
for days, one for swing, and one for grave. If you have a grouped
resource,
like a group of 15 welders and different members of the group work
on
each
shift - say 7 on days, 6 on swing, and 2 on grave - you would have
three
resources listed - day welders max 700%, swing welders max 600% and
grave
welders max 200% and each group would have the base calendar that
describes
their shift's hours of work. If you are listing single individuals
as
resources, like Joe Engineer, you assign him the base calendar that
most
accurately describes his individual hours of work, modified as
needed
to
reflect his true working hours and vacation time, etc. Now if I
have
a
task
starting Monday 8am requiring 24 hours of work and I assign 1 day
shift
worker to it, it will finish Wed at 5pm. IF I assign two day shift
workers,
it will finish Tue 12 noon (if it's effort driven) But if I assign
1
day
shift worker and 1 swing shift worker it will finish Tue 5pm (day
works
mon
day, swing works mon swing, task stops at midnight and resumes when
day
guy
comes back in on Tue morning.) If I assign one guy from each
shift,
the
task will run 24 consecutive hours and starting Mon 8am will finish
Tue
at
8am, exactly as expected, right? (I omitted taking into account
their
possible overlap in hours for simplicity - Mon between 3 and 5
you'd
probably get 4 hours of work done instead of 2 since both guys are
working
together during that period but you get the idea).

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

We work 8 hours in 3 turns 24/7. Project calendar is 24 hours
(24H/day,
168H/month and 30days/month) and Resource calendar is 24 hours .

Task is fixed work = 2760H and given duration = 10days. This
example
gives
1150% Resource Units. I expected 3 times as much, 3450%.

Can project calculate the number resources needed for the task?
 
A

Assist

1 day duration is 24 hours.

Steve House said:
Question about your calendars. Remember durations are *always* stored and
processed internally in hours to the nearest 1/10 minute. Units such as
days, weeks, etc are provided as a convenience but are converted upon entry
and the "hors per day" etc setting on the calendar options page are the
conversion factors used. So when you say a task has a duration of "1 day"
are you thinking that task lasts 8 hours or does it last 24 hours? In other
words, if that 1-day duration task starts Monday at 8am should the schedule
have it end Monday at 5pm or Tuesday at 8am?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Assist said:
Thanks a lot for your replies !
We use AMIGO to manage work cards on the different jobs. (We like to dig
data out of AMIGO and import it into MS Project, but thatâ?Ts another
story).
We like to show the big picture in a Gantt chart. So a C-Check on a
specific
aircraft is one task. We are trying to use MS Project to show witch
aircraft
is worked on (in which hangar) from start date to end date as one task.
We also want to show what kind of resource % that is needed. We like to
show
the Gantt Chart on a big screen in the hangar as a service information to
the
mechanics. At this point we won't use project to manage the mechanics
detailed tasks. If we need to hire in extra mechanics we like to know
when,
how long and how many.

The question to us is how can MS Project calculate the need of resources
correct?

Example:
Project Calendar: 24/7, 8h/d, 40h/w, 30d/m
Task name: MS-AMM, C-Check
Duration: 10 days
Start date: 1-Oct-2007
Deadline is 10-oct-2007

Work: 2760h, Fixed work
Resource: Mechanics

Resource Calendar: I hope we can use one resource calendar, 24/7, 8h/d,
40h/w and 30d/m.
Resource name: Mechanics (There is only one kind of resources)
Unit: 12000% (120 mechanics) (+ hired-in mechanics if needed)

Regards,
Brian




Steve House said:
No no, not saying that at all! Quite the contrary - IMHO Project is an
excellent tool to use for this sort of thing. The periodic maintainance
of
an individual aircraft can very easily be viewed as a project with
observable start and ending times and a unique deliverable being created.
But Project - as does adopting formal Critical Path Methodology in
general,
even when done by paper and pencil - sometimes requires a fresh approach
in
the way one looks at work and scheduling within your organization. For
example, it may be you're not presently looking at your manpower
scheduling
at a fine enough detail to effectively manage the individual workers and
their individual tasks. "Inspect Engines" is not detailed enough.
"Inspect
#1 Engine" is getting better. "Drop # 1 Engine (2 hours)," "Remove
Cowling"
(1 hour), "X-ray #1 Engine's Main Turbine Blades" (6 hours) etc etc is
getting close. Idealy it needs to get down to the point you can use
Project's task list and calculated schedule to determine that an A&P
mechanic needs to show up at a specific location at a clearly
identifiable
date and time with the appropriate parts and tools required to do a
specific
task on a specific part of the airplane and he will be forecast to have
completed it by another specific date and time so that a) you know when
he
can move on to something else that needs his skills to proceed; and b)
whoever has to do the next thing in line after him in that part of the
airplane knows when the first mechanic will be done and out of the way so
that HE can show up ready to do his part of the job.

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



Lets see if I got i right.
Generaly this is not what project is designed for. Do you recoment not
to
use Project for this kind of tasks?


:

One thing to consider. The duration of a task is not normally the
"window
of opportunity" within which the task must be done. Rather it's
length
of
time between when work on the job physically commences and when it is
complete. For a simple example, imagine an incoming aircraft
requiring
only
a single maintenance item that requires 1 person to perform 8
man-hours
of
work. The plane arrives tomorrow morning and must be completed within
10
days. The nature of the work is such that once he starts on it, the
resource must focus 100% of his effort on that specific job - he
can't
'multitask' that activity with other responsibilities. That task is
NOT
a
10 day duration task. Rather it is a 1 day duration task with a
completion
deadline 10 days out. If he CAN multitask and split his time 50/50
between
that task and something else (and you choose to schedule him for both
of
them), it is a 2 day task with the resource assigned 50% and a
deadline
10
days out, and so forth. If two people can share the task with each
devoting
their full effort towards it, then each of them is doing 100% effort
and
each performs 4 hours of the 8 total required and it's a 1/2 day
duration
task with a deadline 10 days out. In each case it is either a .5 or 1
or
2
day duration task occurring within a 10 day window between when it
could
start and when it must be done. It's generally assumed that you
always
want
to schedule it to start AND END as early as possible within that
window
and
would never want lower the resource effort level in order to spread
the
duration to fill the time to the deadline unless you have no other
choice -
your objective is to "git 'er done" as soon as you possibly can that
is
consistent with the other priorities falling outside the project's
universe
and that can be done with the manpower available .

Tasks are always observable physical activity of some sort being
performed
by a resource. The duration is simply the time period over which an
observer will see action taking place on that specific activity as
distinguished from the time period over which he 'might' see activity,
if
you get the difference.

HTH and best of luck

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Hi Steve
Extremely fine answer. I will try out your ideas and get back with
my
results.

A little more info:
Our line of business is in aircraft maintenance, and strongly
regulated.
We
work 8 hours in 3 shifts. The effective work is about 7 hours or
less
in
one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task and
we
have
the aircraft on the ground for max. amount of days (by contract with
customer). So the only variable is resources internally and
externally.
Regards, Brian from Assist


:

If your resource calendar shows 24 hours per day working hours,
that
mean
that ONE man working 100% will perform 24 man-hours of work during
24
hours
of duration. A total of 2760 man-hours of required work to
complete
the
task spread over a duration of 10 24-hour days means that each day
276
man-hours of work will need to be accomplished. 276 hours/24 hours
per
man
= 11.5 men are required, thus 1150% resource units. It also
implies
that
none of them will get any time off for the full 10 day period and
that's
not
likely - machines might work like that but humans simply can't do
it
and
survive! It's not for nothing that around 6 to 8 hours per day is
the
defacto standard workday - that's a biologically driven limit to
human
endurance for 100% functioning beyond which productivity plummets
into
the
toilet and accident rates soar. IMHO it's an incredibly bad
practice
to
routinely schedule people for 10, 12, or 14 hour days and from a
purely
economic standpoint a firm or manager that does it formally or
informally
is
shooting themselves in the foot, incurring long term costs that far
exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT reflect
the
hours
of business of the organization. Rather, it should reflect the
work
hours
of ONE typical generic resource because a task breakdown is down
down
to
the
level of a task being a package of work done by ONE resource or
resource
teak working together and when you add a task to your project you
want
it
to
be scheduled reflecting that reality. The 24 hour project calendar
says
that work proceeds on all tasks 24/7 but that not usual in most
project.
Since tasks are typically assigned to one person and one person
typically
only works about 8 hours per day, the task schedule should reflect
that
it
proceeds at the rate of 8 hours per day between start and finish.
Likewise,
the resource calendar should NOT be a 24 hour calendar because the
resource
calendar for Joe Resource reflects Joe's personal working schedule
and
no
human being works 24/7 for days on end without a break, without a
meal,
without even a nap or what have you yet that's exactly what the 24
hour
calendar says is your physical reality. If you have 3 shifts
covering
in
total the 24 hour period, you have not one resource calendar but
three -
one
for days, one for swing, and one for grave. If you have a grouped
resource,
like a group of 15 welders and different members of the group work
on
each
shift - say 7 on days, 6 on swing, and 2 on grave - you would have
 
S

Steve House

If that's the case, then make sure the Tools/Options/Calendar page has hours
per day set to 24 and hours per week set to 168. "Month" will be
problematic so don't use it for duration entries. Those values set the
conversion factor that Project uses to convert to hours, thus minutes, when
you input a duration as "X Days" or "Y Weeks." It makes a huge difference
because the "8 hour per day" setting says that a task entered as "3 days"
lasts 24 working hours while making it "24 hours per day" says that a task
entered as "3 days" lasts 72 working hours. I think in your original post
you said you had left them at 8/40 and that'll screw everything up. I like
to think of it sort of like the hours per day setting says HOW MANY minutes
out of the day count for duration while the working time calendar sets WHICH
ONES out of the 1440.0 possible minutes in each day will count. Duration is
the total number of minutes the work takes and the working time calendar
determines the day-to-day pattern by which those minutes can get burned up.
While those setting and the Project Calendar usually should be consistent
with each other, changing one doesn't automatically change the other.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Assist said:
1 day duration is 24 hours.

Steve House said:
Question about your calendars. Remember durations are *always* stored
and
processed internally in hours to the nearest 1/10 minute. Units such as
days, weeks, etc are provided as a convenience but are converted upon
entry
and the "hors per day" etc setting on the calendar options page are the
conversion factors used. So when you say a task has a duration of "1 day"
are you thinking that task lasts 8 hours or does it last 24 hours? In
other
words, if that 1-day duration task starts Monday at 8am should the
schedule
have it end Monday at 5pm or Tuesday at 8am?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Assist said:
Thanks a lot for your replies !
We use AMIGO to manage work cards on the different jobs. (We like to
dig
data out of AMIGO and import it into MS Project, but thatâ?Ts another
story).
We like to show the big picture in a Gantt chart. So a C-Check on a
specific
aircraft is one task. We are trying to use MS Project to show witch
aircraft
is worked on (in which hangar) from start date to end date as one task.
We also want to show what kind of resource % that is needed. We like to
show
the Gantt Chart on a big screen in the hangar as a service information
to
the
mechanics. At this point we won't use project to manage the mechanics
detailed tasks. If we need to hire in extra mechanics we like to know
when,
how long and how many.

The question to us is how can MS Project calculate the need of
resources
correct?

Example:
Project Calendar: 24/7, 8h/d, 40h/w, 30d/m
Task name: MS-AMM, C-Check
Duration: 10 days
Start date: 1-Oct-2007
Deadline is 10-oct-2007

Work: 2760h, Fixed work
Resource: Mechanics

Resource Calendar: I hope we can use one resource calendar, 24/7, 8h/d,
40h/w and 30d/m.
Resource name: Mechanics (There is only one kind of resources)
Unit: 12000% (120 mechanics) (+ hired-in mechanics if needed)

Regards,
Brian




:

No no, not saying that at all! Quite the contrary - IMHO Project is
an
excellent tool to use for this sort of thing. The periodic
maintainance
of
an individual aircraft can very easily be viewed as a project with
observable start and ending times and a unique deliverable being
created.
But Project - as does adopting formal Critical Path Methodology in
general,
even when done by paper and pencil - sometimes requires a fresh
approach
in
the way one looks at work and scheduling within your organization.
For
example, it may be you're not presently looking at your manpower
scheduling
at a fine enough detail to effectively manage the individual workers
and
their individual tasks. "Inspect Engines" is not detailed enough.
"Inspect
#1 Engine" is getting better. "Drop # 1 Engine (2 hours)," "Remove
Cowling"
(1 hour), "X-ray #1 Engine's Main Turbine Blades" (6 hours) etc etc is
getting close. Idealy it needs to get down to the point you can use
Project's task list and calculated schedule to determine that an A&P
mechanic needs to show up at a specific location at a clearly
identifiable
date and time with the appropriate parts and tools required to do a
specific
task on a specific part of the airplane and he will be forecast to
have
completed it by another specific date and time so that a) you know
when
he
can move on to something else that needs his skills to proceed; and b)
whoever has to do the next thing in line after him in that part of the
airplane knows when the first mechanic will be done and out of the way
so
that HE can show up ready to do his part of the job.

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



Lets see if I got i right.
Generaly this is not what project is designed for. Do you recoment
not
to
use Project for this kind of tasks?


:

One thing to consider. The duration of a task is not normally the
"window
of opportunity" within which the task must be done. Rather it's
length
of
time between when work on the job physically commences and when it
is
complete. For a simple example, imagine an incoming aircraft
requiring
only
a single maintenance item that requires 1 person to perform 8
man-hours
of
work. The plane arrives tomorrow morning and must be completed
within
10
days. The nature of the work is such that once he starts on it,
the
resource must focus 100% of his effort on that specific job - he
can't
'multitask' that activity with other responsibilities. That task
is
NOT
a
10 day duration task. Rather it is a 1 day duration task with a
completion
deadline 10 days out. If he CAN multitask and split his time 50/50
between
that task and something else (and you choose to schedule him for
both
of
them), it is a 2 day task with the resource assigned 50% and a
deadline
10
days out, and so forth. If two people can share the task with each
devoting
their full effort towards it, then each of them is doing 100%
effort
and
each performs 4 hours of the 8 total required and it's a 1/2 day
duration
task with a deadline 10 days out. In each case it is either a .5
or 1
or
2
day duration task occurring within a 10 day window between when it
could
start and when it must be done. It's generally assumed that you
always
want
to schedule it to start AND END as early as possible within that
window
and
would never want lower the resource effort level in order to spread
the
duration to fill the time to the deadline unless you have no other
choice -
your objective is to "git 'er done" as soon as you possibly can
that
is
consistent with the other priorities falling outside the project's
universe
and that can be done with the manpower available .

Tasks are always observable physical activity of some sort being
performed
by a resource. The duration is simply the time period over which
an
observer will see action taking place on that specific activity as
distinguished from the time period over which he 'might' see
activity,
if
you get the difference.

HTH and best of luck

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Hi Steve
Extremely fine answer. I will try out your ideas and get back
with
my
results.

A little more info:
Our line of business is in aircraft maintenance, and strongly
regulated.
We
work 8 hours in 3 shifts. The effective work is about 7 hours or
less
in
one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task
and
we
have
the aircraft on the ground for max. amount of days (by contract
with
customer). So the only variable is resources internally and
externally.
Regards, Brian from Assist


:

If your resource calendar shows 24 hours per day working hours,
that
mean
that ONE man working 100% will perform 24 man-hours of work
during
24
hours
of duration. A total of 2760 man-hours of required work to
complete
the
task spread over a duration of 10 24-hour days means that each
day
276
man-hours of work will need to be accomplished. 276 hours/24
hours
per
man
= 11.5 men are required, thus 1150% resource units. It also
implies
that
none of them will get any time off for the full 10 day period
and
that's
not
likely - machines might work like that but humans simply can't
do
it
and
survive! It's not for nothing that around 6 to 8 hours per day
is
the
defacto standard workday - that's a biologically driven limit to
human
endurance for 100% functioning beyond which productivity
plummets
into
the
toilet and accident rates soar. IMHO it's an incredibly bad
practice
to
routinely schedule people for 10, 12, or 14 hour days and from a
purely
economic standpoint a firm or manager that does it formally or
informally
is
shooting themselves in the foot, incurring long term costs that
far
exceed
any short term gains. But I digress.

I feel very strongly that the project calendar should NOT
reflect
the
hours
of business of the organization. Rather, it should reflect the
work
hours
of ONE typical generic resource because a task breakdown is down
down
to
the
level of a task being a package of work done by ONE resource or
resource
teak working together and when you add a task to your project
you
want
it
to
be scheduled reflecting that reality. The 24 hour project
calendar
says
that work proceeds on all tasks 24/7 but that not usual in most
project.
Since tasks are typically assigned to one person and one person
typically
only works about 8 hours per day, the task schedule should
reflect
that
it
proceeds at the rate of 8 hours per day between start and
finish.
Likewise,
the resource calendar should NOT be a 24 hour calendar because
the
resource
calendar for Joe Resource reflects Joe's personal working
schedule
and
no
human being works 24/7 for days on end without a break, without
a
meal,
without even a nap or what have you yet that's exactly what the
24
hour
calendar says is your physical reality. If you have 3 shifts
covering
in
total the 24 hour period, you have not one resource calendar but
three -
one
for days, one for swing, and one for grave. If you have a
grouped
resource,
like a group of 15 welders and different members of the group
work
on
each
shift - say 7 on days, 6 on swing, and 2 on grave - you would
have
 
A

Assist

Tools, Option, Calendar is 24h/d and 168h/w.
Mechanics resources is set to 120.000% on the resource sheet.
The project calendar is set to '24 hours', 7 days/week.

Project still calculate the need of resources wrong in the example.


Steve House said:
If that's the case, then make sure the Tools/Options/Calendar page has hours
per day set to 24 and hours per week set to 168. "Month" will be
problematic so don't use it for duration entries. Those values set the
conversion factor that Project uses to convert to hours, thus minutes, when
you input a duration as "X Days" or "Y Weeks." It makes a huge difference
because the "8 hour per day" setting says that a task entered as "3 days"
lasts 24 working hours while making it "24 hours per day" says that a task
entered as "3 days" lasts 72 working hours. I think in your original post
you said you had left them at 8/40 and that'll screw everything up. I like
to think of it sort of like the hours per day setting says HOW MANY minutes
out of the day count for duration while the working time calendar sets WHICH
ONES out of the 1440.0 possible minutes in each day will count. Duration is
the total number of minutes the work takes and the working time calendar
determines the day-to-day pattern by which those minutes can get burned up.
While those setting and the Project Calendar usually should be consistent
with each other, changing one doesn't automatically change the other.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Assist said:
1 day duration is 24 hours.

Steve House said:
Question about your calendars. Remember durations are *always* stored
and
processed internally in hours to the nearest 1/10 minute. Units such as
days, weeks, etc are provided as a convenience but are converted upon
entry
and the "hors per day" etc setting on the calendar options page are the
conversion factors used. So when you say a task has a duration of "1 day"
are you thinking that task lasts 8 hours or does it last 24 hours? In
other
words, if that 1-day duration task starts Monday at 8am should the
schedule
have it end Monday at 5pm or Tuesday at 8am?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks a lot for your replies !
We use AMIGO to manage work cards on the different jobs. (We like to
dig
data out of AMIGO and import it into MS Project, but thatâ?Ts another
story).
We like to show the big picture in a Gantt chart. So a C-Check on a
specific
aircraft is one task. We are trying to use MS Project to show witch
aircraft
is worked on (in which hangar) from start date to end date as one task.
We also want to show what kind of resource % that is needed. We like to
show
the Gantt Chart on a big screen in the hangar as a service information
to
the
mechanics. At this point we won't use project to manage the mechanics
detailed tasks. If we need to hire in extra mechanics we like to know
when,
how long and how many.

The question to us is how can MS Project calculate the need of
resources
correct?

Example:
Project Calendar: 24/7, 8h/d, 40h/w, 30d/m
Task name: MS-AMM, C-Check
Duration: 10 days
Start date: 1-Oct-2007
Deadline is 10-oct-2007

Work: 2760h, Fixed work
Resource: Mechanics

Resource Calendar: I hope we can use one resource calendar, 24/7, 8h/d,
40h/w and 30d/m.
Resource name: Mechanics (There is only one kind of resources)
Unit: 12000% (120 mechanics) (+ hired-in mechanics if needed)

Regards,
Brian




:

No no, not saying that at all! Quite the contrary - IMHO Project is
an
excellent tool to use for this sort of thing. The periodic
maintainance
of
an individual aircraft can very easily be viewed as a project with
observable start and ending times and a unique deliverable being
created.
But Project - as does adopting formal Critical Path Methodology in
general,
even when done by paper and pencil - sometimes requires a fresh
approach
in
the way one looks at work and scheduling within your organization.
For
example, it may be you're not presently looking at your manpower
scheduling
at a fine enough detail to effectively manage the individual workers
and
their individual tasks. "Inspect Engines" is not detailed enough.
"Inspect
#1 Engine" is getting better. "Drop # 1 Engine (2 hours)," "Remove
Cowling"
(1 hour), "X-ray #1 Engine's Main Turbine Blades" (6 hours) etc etc is
getting close. Idealy it needs to get down to the point you can use
Project's task list and calculated schedule to determine that an A&P
mechanic needs to show up at a specific location at a clearly
identifiable
date and time with the appropriate parts and tools required to do a
specific
task on a specific part of the airplane and he will be forecast to
have
completed it by another specific date and time so that a) you know
when
he
can move on to something else that needs his skills to proceed; and b)
whoever has to do the next thing in line after him in that part of the
airplane knows when the first mechanic will be done and out of the way
so
that HE can show up ready to do his part of the job.

HTH

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



Lets see if I got i right.
Generaly this is not what project is designed for. Do you recoment
not
to
use Project for this kind of tasks?


:

One thing to consider. The duration of a task is not normally the
"window
of opportunity" within which the task must be done. Rather it's
length
of
time between when work on the job physically commences and when it
is
complete. For a simple example, imagine an incoming aircraft
requiring
only
a single maintenance item that requires 1 person to perform 8
man-hours
of
work. The plane arrives tomorrow morning and must be completed
within
10
days. The nature of the work is such that once he starts on it,
the
resource must focus 100% of his effort on that specific job - he
can't
'multitask' that activity with other responsibilities. That task
is
NOT
a
10 day duration task. Rather it is a 1 day duration task with a
completion
deadline 10 days out. If he CAN multitask and split his time 50/50
between
that task and something else (and you choose to schedule him for
both
of
them), it is a 2 day task with the resource assigned 50% and a
deadline
10
days out, and so forth. If two people can share the task with each
devoting
their full effort towards it, then each of them is doing 100%
effort
and
each performs 4 hours of the 8 total required and it's a 1/2 day
duration
task with a deadline 10 days out. In each case it is either a .5
or 1
or
2
day duration task occurring within a 10 day window between when it
could
start and when it must be done. It's generally assumed that you
always
want
to schedule it to start AND END as early as possible within that
window
and
would never want lower the resource effort level in order to spread
the
duration to fill the time to the deadline unless you have no other
choice -
your objective is to "git 'er done" as soon as you possibly can
that
is
consistent with the other priorities falling outside the project's
universe
and that can be done with the manpower available .

Tasks are always observable physical activity of some sort being
performed
by a resource. The duration is simply the time period over which
an
observer will see action taking place on that specific activity as
distinguished from the time period over which he 'might' see
activity,
if
you get the difference.

HTH and best of luck

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Hi Steve
Extremely fine answer. I will try out your ideas and get back
with
my
results.

A little more info:
Our line of business is in aircraft maintenance, and strongly
regulated.
We
work 8 hours in 3 shifts. The effective work is about 7 hours or
less
in
one
shift. The mechanics is out of the team for vacation.
We know the amount of man-work-hours for every maintenance task
and
we
have
the aircraft on the ground for max. amount of days (by contract
with
customer). So the only variable is resources internally and
externally.
Regards, Brian from Assist


:

If your resource calendar shows 24 hours per day working hours,
that
mean
that ONE man working 100% will perform 24 man-hours of work
during
24
hours
of duration. A total of 2760 man-hours of required work to
complete
the
task spread over a duration of 10 24-hour days means that each
day
276
man-hours of work will need to be accomplished. 276 hours/24
hours
per
man
= 11.5 men are required, thus 1150% resource units. It also
implies
that
none of them will get any time off for the full 10 day period
and
that's
not
likely - machines might work like that but humans simply can't
do
it
and
survive! It's not for nothing that around 6 to 8 hours per day
is
the
defacto standard workday - that's a biologically driven limit to
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top