S
Steve
I have a few tasks that require some equipment to be on them for 24 hours a
day for about 4 days at a time. There are only 4 pieces of such equipment,
and many tasks that require their use. Once the equipment finishes at one
location, it moves on to the other. I had one of these machines finish its
work on Monday morning 8/4/08. It started last Thursday, 7/31/08. For some
reason, Project is telling me that it only took 3 days to complete when it
actually took about 5. I have a 24/7 calender assigned to both the resource
and the task, Why is the duration being wrongly altered?
day for about 4 days at a time. There are only 4 pieces of such equipment,
and many tasks that require their use. Once the equipment finishes at one
location, it moves on to the other. I had one of these machines finish its
work on Monday morning 8/4/08. It started last Thursday, 7/31/08. For some
reason, Project is telling me that it only took 3 days to complete when it
actually took about 5. I have a 24/7 calender assigned to both the resource
and the task, Why is the duration being wrongly altered?