S
ss
I'm trying to develop a schedule for a 24 hr/day project, including all
resources. There will be two crews on this project working from 6:00 AM to
6:00 PM for the first shift. The 2nd shift will work from 6:00 PM to 6:00
AM. I can only assume that I would develop a day shift resource and a night
shift resource and assign the work hours accordingly? Also, the Gant chart
does not appear to depict the correct start time of 6:00, it defaults to
8:00. I would like to have the works hours accurately shown on the Gant
chart for both shifts. This is most likely a simple question for those more
experienced - regardless I am hopeful to receive some help. Thanks in
advance.
resources. There will be two crews on this project working from 6:00 AM to
6:00 PM for the first shift. The 2nd shift will work from 6:00 PM to 6:00
AM. I can only assume that I would develop a day shift resource and a night
shift resource and assign the work hours accordingly? Also, the Gant chart
does not appear to depict the correct start time of 6:00, it defaults to
8:00. I would like to have the works hours accurately shown on the Gant
chart for both shifts. This is most likely a simple question for those more
experienced - regardless I am hopeful to receive some help. Thanks in
advance.