The problem with using the 24 hour calendar, as I see it, is that if it's
the Project calendar the assumption is that all tasks will proceed 24/7
from
the time they start until they're done. That's not often the case. You
usually assign a task to a specific team that works 1 and only 1 shift.
It
might be day or swing or graveyard but a 40 hours task won't run from 8am
Mon until Tue evening with resources on successive shifts relieving each
other, it'll run for 5 working days with the resource assigned doing 8
hours
day 1, 8 hours day 2, 8 hours day 3 etc with the task standing down for
the
time that one resource isn't working and it doesn't matter if that
resource
is day shift or swing shift or grave shift. The FIRM may operate 24/7
but
the ONE resource assigned to each specific task still only goes for 8
hours
at a stretch with 16 hours of non-activity following each work period of
the
resource doing that specific task. IMHO, if you have ONE task being done
in
turn by Joe Dayshift, Mary Swingshift, and Fred Graveshift relieving each
other in turn, you're not breaking the tasks down into sufficient detail
to
effectively manage the work.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
MS Project contains a 24 hour calendar by default. To see it,
Tools/Change
Working Time and then hit the dropdown at the top of the window. If it
is
not there, hit the new button and you can create it by highlighting all
days
and changing the hours. Make sure you save a unique name so nothing
gets
overwritten. However, you will probably not have to do that part.
Using these calendars is just as easy. Create tasks as you normally
would
do. To change the calendar assigned to a specific task, double click
the
task, pull the advanced tab, change the calendar to 24 hours.
To assign the calendar to multiple tasks, highlight all the tasks
desired
and select the task information icon (looks like file folders) in the
toobar,
then advanced.
The calendar will apply unless an individual resource has its own
calendar
which overrides the global settings.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project
:
I use MS Project to schedule maintenance in a chemical plant. My
typical
tasks are 1 to 6 hours in length and we just work days. Several times
a
year, we have a shutdown and go on a 24 hour schedule. Does anyone
know
how
to set up multiple shifts in MS Project? Some of the tasks will work
around
the clock for several days but most will be on days. The night shift
has
less resources than the day shift.