shahid_chowdhury
Platform: PS 2007, SPI, INF UPDATE (EPM)
I would like to have 2 calendars for users to use. 1st is the standard 9-5
Mon-Fri in addition to this we want to have a 24 hr calendar for smaller time
sensitive projects. These projects will be to monitor and maintain 24 hr
work.
Ideally I would like to create an Enterprise template that can do this. I
know in PWA (as admin) I can create multiple calendars, but how can I tie
this with an Enterprise Template so that the users can use specific calendars
for these types of projects (via templates).
Also what is the impact on PWA updates by team members as we are tracking
via "Actual work done and work remaining" method.
Thanks.
I would like to have 2 calendars for users to use. 1st is the standard 9-5
Mon-Fri in addition to this we want to have a 24 hr calendar for smaller time
sensitive projects. These projects will be to monitor and maintain 24 hr
work.
Ideally I would like to create an Enterprise template that can do this. I
know in PWA (as admin) I can create multiple calendars, but how can I tie
this with an Enterprise Template so that the users can use specific calendars
for these types of projects (via templates).
Also what is the impact on PWA updates by team members as we are tracking
via "Actual work done and work remaining" method.
Thanks.