D
Dougie Robertson
WE operate 24/7 and the projects will run over approximatly 10 days, there is
multiple teams on 12 hr shifts and I have resorses split to DAYSHIFT &
NIGHTSHIFT resorce calanders.
When entering the team members, the gantt chart is lenthening the bar way
beyond the job time, but it still says 3 hours for example. Yet I have a bar
of 15, 16 hours.
The resorses are from the correct shift to be working but it still changes
things. Also the safety meetings at the begining of the shift with all the
shift tend to completly muck up the resorce allocations.
How do I keep the task lenth correct, regardless of who is allocated?
CAn I change the times to the 24 hr. clock and get rid of the AM & PM.
multiple teams on 12 hr shifts and I have resorses split to DAYSHIFT &
NIGHTSHIFT resorce calanders.
When entering the team members, the gantt chart is lenthening the bar way
beyond the job time, but it still says 3 hours for example. Yet I have a bar
of 15, 16 hours.
The resorses are from the correct shift to be working but it still changes
things. Also the safety meetings at the begining of the shift with all the
shift tend to completly muck up the resorce allocations.
How do I keep the task lenth correct, regardless of who is allocated?
CAn I change the times to the 24 hr. clock and get rid of the AM & PM.