X
xlsstudent
Hi,
I have a schedule where we can have meetings with our clients on ONLY
specific days like Mondays and Thursdays only. Also, these are 4 hour
meetings and task has to completed in a single day. I have linked the tasks
based on resources. Ex. Res1. task1. After finishing task1, take up meeting.
After meeting, collect requirements and develop high level design.
Currently I have constrained meeting to happen on a specific day. Now if I
change the start date of task1, it automatically pushes the meeting day to a
Wednesday, which is not good. I have about 100 meetings which should happen
only on mon or thursdays. Also, if task1 is 6 hrs, MSP allocates 2 hrs of
meeting to days and rest to day2. Is there any way of constraining a task be
performed on a specific days of the week? Also constraining that the task has
to completed within same day or more the whole task to next day? Pls help..!!
I have a schedule where we can have meetings with our clients on ONLY
specific days like Mondays and Thursdays only. Also, these are 4 hour
meetings and task has to completed in a single day. I have linked the tasks
based on resources. Ex. Res1. task1. After finishing task1, take up meeting.
After meeting, collect requirements and develop high level design.
Currently I have constrained meeting to happen on a specific day. Now if I
change the start date of task1, it automatically pushes the meeting day to a
Wednesday, which is not good. I have about 100 meetings which should happen
only on mon or thursdays. Also, if task1 is 6 hrs, MSP allocates 2 hrs of
meeting to days and rest to day2. Is there any way of constraining a task be
performed on a specific days of the week? Also constraining that the task has
to completed within same day or more the whole task to next day? Pls help..!!