We have Project Server 2007
The Project I am creating needs a 4x10 calendar.
All resources associated with this project has the standard United States
Calendar as their base calendars.
I went into each task and updated them to 4x10 and while saving the project
also changed the Project Calendar to 4x10, but the tasks are still showing
the duration as if it were an 8hr regular day.
The 4x10 calendar is not taking effect, what could I be doing wrong?
Please advise. Thanks!
The Project I am creating needs a 4x10 calendar.
All resources associated with this project has the standard United States
Calendar as their base calendars.
I went into each task and updated them to 4x10 and while saving the project
also changed the Project Calendar to 4x10, but the tasks are still showing
the duration as if it were an 8hr regular day.
The 4x10 calendar is not taking effect, what could I be doing wrong?
Please advise. Thanks!