6 hours per day

D

don.lowe

Hi
I have set one day to equal 6 hours Tools --> Options --> Calender.
When I open the Resource Usage View, work is still allocated at 8 hours
per day.
How do I make sure that the work day is limited to 6 hours?
 
J

JulieS

Hello Don,

You need to modify the calendar through Tools > Change Working time
and edit the start and end time all working days to 6 hours per day.

Please see FAQ #5 "Default working hours" at
http://project.mvps.org/faqs.htm

for details.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
A

Andrew Lavinsky

You still need to create a 6 hour work calendar (Tools > Change Working Time),
then assign that calendar to your project resources. Otherwise, they will
continue on their Standard 8 hour calendar.

It's a bit complicated, yes.

-A
 
D

don.lowe

Thank you, Julie and Andrew your recomendations seem to have worked.
regards
Don
 