L
Lloyd Lewis
I'm baffled. I have set the default values for working hours on the
Schedule tab of the Options window to be as follows:
Default start time: 8:00 am
Default end time: 4:30 pm
Hours per day: 7.5
Hours per week: 37.5
Yet when I open a new plan, the Change Working Time window reports:
use default:
From: 8:00 am to 12:00 pm
From: 1:00 pm to 5:00 pm
As I enter task durations in days, it is obvious from the Gnatt chart
display that Project is using 8 hour days. I can't seem to find how to
correct this situation without a lot of brute force methods. Anyone know
how to ensure Project defaults to a 7.5 hour day so that these two windows
agree?
Lloyd
Schedule tab of the Options window to be as follows:
Default start time: 8:00 am
Default end time: 4:30 pm
Hours per day: 7.5
Hours per week: 37.5
Yet when I open a new plan, the Change Working Time window reports:
use default:
From: 8:00 am to 12:00 pm
From: 1:00 pm to 5:00 pm
As I enter task durations in days, it is obvious from the Gnatt chart
display that Project is using 8 hour days. I can't seem to find how to
correct this situation without a lot of brute force methods. Anyone know
how to ensure Project defaults to a 7.5 hour day so that these two windows
agree?
Lloyd