M
markb
I have a project that includes tasks that run around the clock for 8 days. I
would like to schedule on a 5 day standard calendar while including these
tasks.
For example, I have a worker preparing samples during their normal work time
and then the samples get placed into an oven for 8 days (24 hrs per day)
without being removed. The oven shuts off automatically when the 8 days are
complete. The parts are removed on the next normal work day.
How can I do this in Project 2007?
would like to schedule on a 5 day standard calendar while including these
tasks.
For example, I have a worker preparing samples during their normal work time
and then the samples get placed into an oven for 8 days (24 hrs per day)
without being removed. The oven shuts off automatically when the 8 days are
complete. The parts are removed on the next normal work day.
How can I do this in Project 2007?