B
Barbara G
We are struggling with getting enough information into the project without it
being too much information for the resources. PMs and Management don’t feel
the 8/80 rule gives them enough information on the individual tasks. Some PMs
are actually using two different plans, one that they use in EPM for tracking
time and an off line version with more detail. We recognize that it would be
a burden to have the resource log time for each 1 hour activity that they do.
How do we bridge the gap between giving the managers the depth of data that
they need without overburdening the resources?
being too much information for the resources. PMs and Management don’t feel
the 8/80 rule gives them enough information on the individual tasks. Some PMs
are actually using two different plans, one that they use in EPM for tracking
time and an off line version with more detail. We recognize that it would be
a burden to have the resource log time for each 1 hour activity that they do.
How do we bridge the gap between giving the managers the depth of data that
they need without overburdening the resources?