Patty B
I have a manufacturing job that will take 10 hours. We work one 8-hour
shift. If i start the job on Monday, May 19, 2008 at 8am I need to calculate
what day and time it will finish, which is Tuesday at 10am. (8 hours on
Monday and 2 hours on Tuesday). I then need to add the number of hours for
the next job to complete the schedule the week. Any suggestions?
shift. If i start the job on Monday, May 19, 2008 at 8am I need to calculate
what day and time it will finish, which is Tuesday at 10am. (8 hours on
Monday and 2 hours on Tuesday). I then need to add the number of hours for
the next job to complete the schedule the week. Any suggestions?