J
Jaime
Hi, as the title says I have a couple of questions.
First of all, I must say English is not my mother language, but I will try
and explain myself as best as I can. For those of you who wonder why I don't
post it in the Spanish community, well I think the English one is more active
and therefore have more probabilities of getting a reply.
My first question would be, is there a way to change the duration of a
project, and by doing so, change the duration of the tasks and the links
between the end of one task and the beginning of the next one in the same
proportion?
I have some project files that suit me for several projects, depending if
they are for the construction of a railroad, or a highway, or the writing of
a project... And I only have to adapt them to the duration I want each time.
For example, say I have a project with duration of 12 months where task one
takes place during the first month and after four days task two begins and
continues on till the end of month two. And now I would like to adjust the
project to duration of 6 months, where month one should be 15 days, task two
start two days later and take place during the next thirteen days. Get what I
am looking for?
I can do this, and actually this is how I do it, by a 3 rule calculation,
but it would save me a lot of time if there was an easy way of doing it
inside MS Project.
And my second enquiry, is there any way to tell MS Project that I would like
connecting arrows between tasks to be displayed in red only if they go from
one critical task to another one, and not as it does right now displaying red
arrows all those that come from a critical task?
Thanks for reading and looking forward to getting some answers.
Best regards,
Jaime
First of all, I must say English is not my mother language, but I will try
and explain myself as best as I can. For those of you who wonder why I don't
post it in the Spanish community, well I think the English one is more active
and therefore have more probabilities of getting a reply.
My first question would be, is there a way to change the duration of a
project, and by doing so, change the duration of the tasks and the links
between the end of one task and the beginning of the next one in the same
proportion?
I have some project files that suit me for several projects, depending if
they are for the construction of a railroad, or a highway, or the writing of
a project... And I only have to adapt them to the duration I want each time.
For example, say I have a project with duration of 12 months where task one
takes place during the first month and after four days task two begins and
continues on till the end of month two. And now I would like to adjust the
project to duration of 6 months, where month one should be 15 days, task two
start two days later and take place during the next thirteen days. Get what I
am looking for?
I can do this, and actually this is how I do it, by a 3 rule calculation,
but it would save me a lot of time if there was an easy way of doing it
inside MS Project.
And my second enquiry, is there any way to tell MS Project that I would like
connecting arrows between tasks to be displayed in red only if they go from
one critical task to another one, and not as it does right now displaying red
arrows all those that come from a critical task?
Thanks for reading and looking forward to getting some answers.
Best regards,
Jaime