N
Naomin
I want to start development on a relatively certain date, but can’t until
funding and resources are acquired. These do not depend on anything else in
the plan, they just come when they come. Also, development will not start
the moment those are acquired, as a lot of other things must happen before
then. How can I make the development line have resources and funding as
predecessors, but keep that line planned for a 10/21 start?
I looked at other questions on this list but couldn't quite apply that
learning to this question - although I think the answer will be similar!
thanks.
funding and resources are acquired. These do not depend on anything else in
the plan, they just come when they come. Also, development will not start
the moment those are acquired, as a lot of other things must happen before
then. How can I make the development line have resources and funding as
predecessors, but keep that line planned for a 10/21 start?
I looked at other questions on this list but couldn't quite apply that
learning to this question - although I think the answer will be similar!
thanks.