E
E Michael Jakins
I have a task on my Plan which was to do 200 tests over a 8 day period. 70%
have been completed, but time has run out and the task is being "closed" (The
tests are being added to latter work / section in the Project.) We want to
show the task as "stopped" but not 100% finished.
I have had this type of problem before where a task is stopped mid way
through planned work. It always seems to be wrong to mark it as 100%.
Particularly when as in this instance the time is still as in the original
period. Equally we I would not want to make this into 200 seperate tasks -
even then what would I do with the 60 which do not happen?
MS Project does not seem to have a way of properly reflecting this situation.
have been completed, but time has run out and the task is being "closed" (The
tests are being added to latter work / section in the Project.) We want to
show the task as "stopped" but not 100% finished.
I have had this type of problem before where a task is stopped mid way
through planned work. It always seems to be wrong to mark it as 100%.
Particularly when as in this instance the time is still as in the original
period. Equally we I would not want to make this into 200 seperate tasks -
even then what would I do with the 60 which do not happen?
MS Project does not seem to have a way of properly reflecting this situation.