J
JNB
Hi all,
According to HA102118001033, the following is an exception to Late Finish =
Deadline condition;
if the late start minus the lag is earlier than the deadline for one of the
task's successors, the late finish equals that successor task's late start
minus the lag.
I would appreciate if you can give an example of a case that creates the above
condition.
Thanks for any feeedback.
Best Regards - JNB
According to HA102118001033, the following is an exception to Late Finish =
Deadline condition;
if the late start minus the lag is earlier than the deadline for one of the
task's successors, the late finish equals that successor task's late start
minus the lag.
I would appreciate if you can give an example of a case that creates the above
condition.
Thanks for any feeedback.
Best Regards - JNB