A resource with multiple calendars

S

sharma

Hi,

Our company changed the working hours from 7.5 hours to 8 hours. we want to
keep projects that are in progress with 7.5 hours but we want to keep new
projects with 8 hours. with this secnario, all the resources will need two
calendars. Is it possible to create two calendars for a resource? Is there a
better solution to handle projects with 7.5 hours and 8 hours.

thanks
 
R

reza

Sharma....

why u don't use project calendars,
create a new calendars, give it name with i.e "7.5H Calendar" and second one
"8H Calendar". Go to Tools > Change Working Time > Create New Calendar >
Choose Create new base calendar > change calendar name > OK. Click options
and make change there. Create new one for 8 hrs.
After that, applying this calendar to projects. Use "7.5 Calendar" to
project who have resource working for 7.5 hrs and apply "8H Calendar" to
project who have resource working for 8 hrs. Go to Project > Project
Information > Calendar, then choose calendar that you want to use.
Or you can create resource calendars also, but this more complicated. at
least you need create 2 calendar per resource.
wish this will help you.

reza
 