sharma
Hi,
Our company changed the working hours from 7.5 hours to 8 hours. we want to
keep projects that are in progress with 7.5 hours but we want to keep new
projects with 8 hours. with this secnario, all the resources will need two
calendars. Is it possible to create two calendars for a resource? Is there a
better solution to handle projects with 7.5 hours and 8 hours.
thanks