G
greg
I am trying to avoid an issue i am having where i set the standard day to 8
hour days (tools/Options/Calendars) and then provide an offshore caledar for
both specific tasks and resources. There are discrepecines in how project
calculates duration for those that have the 7 day a week/12 hour day
calendars assigned to them. I just want it to go, if 7 day/week task, count
from this start date to this finish date for the duration. instead if says
well the work is done on 1 day, but that 1 day is 1.5 standard days. So a 21
day task with a calendar and resource set at 7 days/week/12 hour shift ends
up being 35 days on the MS project duration column.
Is there a way i can calculate it myself, purely on the difference between
the start and finish days? like with a formula or something?
any help, most appreciated
hour days (tools/Options/Calendars) and then provide an offshore caledar for
both specific tasks and resources. There are discrepecines in how project
calculates duration for those that have the 7 day a week/12 hour day
calendars assigned to them. I just want it to go, if 7 day/week task, count
from this start date to this finish date for the duration. instead if says
well the work is done on 1 day, but that 1 day is 1.5 standard days. So a 21
day task with a calendar and resource set at 7 days/week/12 hour shift ends
up being 35 days on the MS project duration column.
Is there a way i can calculate it myself, purely on the difference between
the start and finish days? like with a formula or something?
any help, most appreciated