J
jleifb
I have a grouping of milestone tasks that will be reported on for metrics at
the top of the plan. Is there a way to have a task in the plan update the
milestone/task at the top as the task becomes complete. So the top of the
plan would be for metrics, then below that would be the actual project plan.
As the tasks below come to completion, they would automatically update the
milestone tasks above. Is there an easy way to do this?
the top of the plan. Is there a way to have a task in the plan update the
milestone/task at the top as the task becomes complete. So the top of the
plan would be for metrics, then below that would be the actual project plan.
As the tasks below come to completion, they would automatically update the
milestone tasks above. Is there an easy way to do this?