A
Al Lavassani
I want to be able to track the remaining available budget that I have as the
project progress. I start the project with a defined budget at the beginning,
but I want to track what's the remaing budget as my resources are using
hours.
Currently, I use an Excel sheet where I define the budget, and use a formula
to multiply the no. of hours spent by each resource by rate, then substract
the total from the remaining budget. I don't know how to apply this in
Project. I would like to have a field showing the remaining budget.
Any hint or advice?
Thanks,
Al Lavassani
project progress. I start the project with a defined budget at the beginning,
but I want to track what's the remaing budget as my resources are using
hours.
Currently, I use an Excel sheet where I define the budget, and use a formula
to multiply the no. of hours spent by each resource by rate, then substract
the total from the remaining budget. I don't know how to apply this in
Project. I would like to have a field showing the remaining budget.
Any hint or advice?
Thanks,
Al Lavassani