J
Jac
To whom it may concern,
I'm a user of MS Project 2003, I'm trying to enter a lag time into 1 of my
project's 3-day-task (10/7/06 - 10/9/06); which by default the start time was
8:00am and the finish time was 5:00pm based on the Standard Calendar & it
was applied throughout the duration. But after I entered the lag time of 40%
into that mentioned task, the start time changed to 9:36am & the finish time
of that task was 9:36am as well throughout the duration with the start date
on 10/7/06 - 10/10/06!
Initially, I thought that MS Project would calculate the inserted lag time
by multiplying the first 4 working hours (8:00am - 12:00noon) with 40% &
added the product to 8:00am in oder to get the start time of 9:36am. So, I
tried again with 50% of lag time, but now the start time changed to 1:00pm &
the finish time is 12:00am. I'm wondering how actually the lag time is being
calculated after it was inserted? Please advise......
Thanking in advanced.
I'm a user of MS Project 2003, I'm trying to enter a lag time into 1 of my
project's 3-day-task (10/7/06 - 10/9/06); which by default the start time was
8:00am and the finish time was 5:00pm based on the Standard Calendar & it
was applied throughout the duration. But after I entered the lag time of 40%
into that mentioned task, the start time changed to 9:36am & the finish time
of that task was 9:36am as well throughout the duration with the start date
on 10/7/06 - 10/10/06!
Initially, I thought that MS Project would calculate the inserted lag time
by multiplying the first 4 working hours (8:00am - 12:00noon) with 40% &
added the product to 8:00am in oder to get the start time of 9:36am. So, I
tried again with 50% of lag time, but now the start time changed to 1:00pm &
the finish time is 12:00am. I'm wondering how actually the lag time is being
calculated after it was inserted? Please advise......
Thanking in advanced.