About Lag Time

C

Charmingpri

For Example

Task A 2 d wed,thu
Task B 3d fri,mon,tue
Task C 5 d Parallel to Task A

In case I introduce lag for 3 days between Task A and Task B,my taskb will
start by wed.(sat & sun are non working days).But instead i want taskb to
start by mon.(calculating 3days lag as fri,sat & sun between task a and task
b).
Also TaskC is parallel to Task A.

How do i do this.
Please help.
Very urgent
 
J

Jan De Messemaeker

Hi,

Enter the lag as 3ed (elapsed days)
Maybe different in other languages!
You can put a Start to Start relationship A to C.
 
C

Charmingpri

Hi

Thank you.
It is Working.

Jan De Messemaeker said:
Hi,

Enter the lag as 3ed (elapsed days)
Maybe different in other languages!
You can put a Start to Start relationship A to C.
 