M
Micheal
Hi,
when we make administrative project what we assign maximum units and
assignments units to resources whether these resources are already worked on
other projects.
If we assign maximun units or assignments units 100 percent to theses
resources then it will overallocation for them . and those resources will
show in RED color in the Resource Sheet. we will set maximun units and
assigments to 100 % or 0 % for them or something else .
and what we will do for their request/demand settings in administrative
project .
and what is effect in scheduling of the project if we set request or demand
for the resource in administrative and normal project.
pls reply me soon
Regards
Micheal
when we make administrative project what we assign maximum units and
assignments units to resources whether these resources are already worked on
other projects.
If we assign maximun units or assignments units 100 percent to theses
resources then it will overallocation for them . and those resources will
show in RED color in the Resource Sheet. we will set maximun units and
assigments to 100 % or 0 % for them or something else .
and what we will do for their request/demand settings in administrative
project .
and what is effect in scheduling of the project if we set request or demand
for the resource in administrative and normal project.
pls reply me soon
Regards
Micheal